Installation
Before installing the machine, the following criteria must be met:
•
The machine must be fully intact.
•
The machine may only be connected using the power cable provided.
•
The machine's main switch is to be used as an all-pole separator.
•
A suitable gas supply (see Chapter 3.1 and 3.2) must be provided.
The stand-alone unit may only be operated while in an upright position. Ensure
that there is sufficient clearance (> 150 mm) in front of the ventilation slots.
To install the machine, perform the following steps in the specified order:
1. Place the machine on a hard, level floor and make sure that the machine is stable.
- Ensure that a clearance of at least 150 mm is maintained between all ventilation slots
and other objects.
-
Make sure that the installation location is chosen such that no nominal tensile stress is
placed on the cables and lines when using the machine.
2. Mount the plasma generator in your system using suitable M5 screws. Follow the drilling
pattern of the mounting plate (see figure below) on which the generator is delivered. The
screws for clamping the plasma generator and cable assembly (incl. HV cable) must not be
loosened!
3. Connect a suitable 6 mm hose for supplying compressed air to the compressed air
maintenance unit. Set the operating pressure to at least 4 bar.
4. Open the cover on the machine for the mains connection and connect the mains connection
cable to the machine.
5. Plug the mains connection cable into a suitable power socket with earthing pins.
If in doubt, check if the protective earth contact of the power socket is functional.
✓
The machine is installed.
Attention
–
Damage to machine!
The stand-alone unit and plasma generator must be set up and fastened in a stable
manner.
Always ensure that there is no nominal tensile stress on the cables.
Non-compliance will damage the machine and/or its components beyond repair!