6.0 Operation
After you finished the installation and configuration, you can start switch the equipment to start
charging the battery from PV array installed. Before power on, please
Double check the V
oc
(Voltage of open circuit)of PV array is less than 150VDC
Double check the PV array wires are connected securely in right polarity
Following switch need to be switched on one by one:
Switch of the battery
Switch of the PV array
Then, you can press the “
”Power On/Off button on front panel to switch on the MPPT
charger controller. If system self-testing is OK, the MPPT will start deliver charging to battery
connected and LCD will display system status page.
6.1 Viewing system status
You will see first page which shows the system status.
Output 80V 60A
Input 120V 60A
PV voltage high
Alarm #25
Fig6-1System status page