![Taylor C723 Operator'S Manual Download Page 34](http://html.mh-extra.com/html/taylor/c723/c723_operators-manual_822762034.webp)
6-2
OPERATING PROCEDURES
Model C723
Operating Procedures
6
Figure 6-3
WARNING!
Use extreme caution
when
handling the beater assembly.
The scraper blades are
very sharp and may cause injury.
6. Before installing the beater assembly, check the
scraper blades. If they are in good condition, take
one of the scraper blades and slip it under the hook
at the front of the beater. Wrap the blade around the
beater, following the helix and pushing the blade
down onto the helix as you wrap. At the back end of
the beater, slip the blade under the hook.
Figure 6-4
7. Repeat this step for the second scraper blade.
8. Holding the beater securely, slide the beater into the
freezing cylinder about 1/3 of the way in. Looking into
the freezing cylinder, align the hole at the rear of the
beater with the flats on the end of the driveshaft.
Figure 6-5
9. Slide the beater the remainder of the way into the
freezing cylinder and over the end of the driveshaft.
The beater should fit snugly, but not so tightly that the
beater cannot be turned slightly to engage the
driveshaft.
10. Make sure the beater assembly is in position over the
driveshaft. Turn the beater slightly to make certain
that the beater is properly seated. When in position,
the beater will not protrude beyond the front of the
freezing cylinder.
11. Repeat these steps for the other side of the machine.
12. To assemble the freezer door, place the door gaskets
into the grooves on the back of the freezer door. Slide
the front bearings over the baffle rods. The flanged
edges should be against the door.
Do not
lubricate
the gaskets or bearings.
13. Slide the two O-rings into the grooves on each prime
plug. Apply an even coat of Taylor Lube to the
O-rings and shafts.
Figure 6-6
101427
11466
11467
11468
Apply the appropriate
Taylor approved food safe lubricant.
Summary of Contents for C723
Page 14: ...3 4 SAFETY Model C723 Safety 3 Notes ...
Page 42: ...6 10 OPERATING PROCEDURES Model C723 Operating Procedures 6 Notes ...
Page 48: ...9 2 PARTS REPLACEMENT SCHEDULE Model C723 Parts Replacement Schedule 9 Notes ...
Page 52: ...10 4 LIMITED WARRANTY ON EQUIPMENT Model C723 Limited Warranty on Equipment 10 Notes ...
Page 56: ...11 4 LIMITED WARRANTY ON PARTS Model C723 Limited Warranty on Parts 11 Notes ...