TB9300 Installation and Operation Manual
Installation
93
© Tait Limited March 2016
5.6.3
Connecting DC Power
The PMU is designed to accept a nominal 12VDC, 24VDC or 48VDC
input (depending on the model) with negative or positive ground. There is
a minimum DC startup threshold to prevent damaging a battery which has
little capacity left.
You must connect the DC supply from the battery to the PMU via a fuse or
DC-rated circuit breaker with the appropriate rating, as shown in the table
below. The circuit breaker must have a contact separation of 3mm, an
interrupt capacity of 1000A or more, and an inrush current capability of at
least 500A for a minimum of 3.5ms.
Notice
The inrush current is not affected by the state of the DC mod-
ule on/off switch on the PMU. This switch does not disconnect power
from the DC converter itself. It disables the converter by switching off
its control circuitry. Even when the DC converter is off, the DC input is
still connected to its power circuitry.
The DC input leads should be of a suitable gauge to ensure less than 0.2V
drop at maximum load over the required length of lead.
Terminate and insulate the DC input leads to protect them from
accidentally shorting to the subrack if the PMU is removed before the leads
are disconnected. Protective covers for the DC terminals are supplied with
each PMU. We recommend a screw torque of 18–20lbf·in (2–2.25N·m).
Nominal Supply
Voltage
Input Voltage
Range
Circuit Breaker/
Fuse Rating
a
a. The actual current consumption of the base station will be lower than these re-
quirements (refer to the Specifications Manual for more information).
Recommended
Wire Gauge
b
b. For a length of 5ft to 6.5ft (1.5m to 2m) (typical).
12VDC
10VDC to 16.8VDC
60A
2AWG / 35mm
2
24VDC
20VDC to 33.6VDC
30A
5AWG / 16mm
2
48VDC
40VDC to 60VDC
15A
8AWG / 8mm
2
Summary of Contents for TB9300
Page 10: ...10 Preface TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 32: ...32 Description TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 76: ...76 Installation TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 102: ...102 Troubleshooting TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 116: ...116 Replacing Modules TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 138: ...138 TB9300 Installation and Operation Manual Tait Limited March 2016...