Mechanical Assembly
This section illustrates the main mechanical components of the base
station.
Figure 1.1
below shows the configuration for a typical dual 50W base
station. The subrack has six slots, numbered from right to left as viewed
from the front of the subrack. The PMU occupies slots 5 and 6, with the
reciters in slots 1 and 2. The two PAs are mounted vertically in slots 3 and
4 with the heatsinks facing each other. The airflow separator between the
PAs helps to direct the cooling airflow evenly through each heatsink. The
PMU and each pair of reciters and PAs have their own cooling fans.
The front panel can be easily removed from the subrack by undoing two
quick-release fasteners. Refer to
“Replacing Modules” on page 103
for
more details.
.
Figure 1.1
Mechanical assembly - dual 50W base station with front panel
b
front panel
i
reciter 1
c
subrack
j
module retaining clamp
d
PMU
1)
subrack interconnect board
e
PA 2
1!
airflow separator
f
PA 1
1@
plastic guide rail
g
cable retaining clip
1#
subrack interconnect board retaining clamp
h
reciter 2
1$
front panel fastener
b
c
d
e
f
g
h
i
j
1)
1@
1#
1$
1!
Summary of Contents for TB9300
Page 10: ...10 Preface TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 32: ...32 Description TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 76: ...76 Installation TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 102: ...102 Troubleshooting TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 116: ...116 Replacing Modules TB9300 Installation and Operation Manual Tait Limited March 2016...
Page 138: ...138 TB9300 Installation and Operation Manual Tait Limited March 2016...