SIDE WALL ASSEMBLY 

(GRILLED & SOLID PARTITIONS)

NoTE:

  The U-channel required for a solid wall partition is 94 1/2" long

  The U-channel required for a grilled wall partition is 46" long

STEP 1

First, select the U-channel for the type of wall partition to be installed. Install 

one U-channel in the center on either the corner or outside wall at + or - 1” 

above the stall floor.

STEP 2

cut all the necessary lumber to a length 1/4" to 3/8" less than the distance 

measured between the inside faces of the U-channels.

STEP 3

Installing the lumber in the U-channels

  3a.  Slide the first board down the U-channels all the way to the floor and  

ensure that it is level.

  3b. Firmly secure with the screws provided.

NoTE: For solid partition walls

  -  Install all remaining boards and secure with the screws provided

   -  Install the two 94” wall braces (one each side) with the screws provided.

STEP 4

 NoTE: Remaining steps are for grill partition walls.

    Install all remaining boards ensuring that they come to a height of 1 1/8" 

above the top of the U-channels. It may be required to rip cut a board to 

achieve the correct height.

STEP 5

Install  the  rubber  grommets  as  shown  in  Detail  D  on  page  5  for  both  the 

bottom grill channel and the corresponding top grill channel.

NoTE:

   Use a soft face mallet or your fingers to install the rubber grommets into 

place.

STEP 6

Install the bottom grill channel flush with the top of the U-channels.

NoTE:

  -  For a 10' partition wall, two 6' and two 4' grill channel are utilized

  -  For a 12' partition wall, two 6' grill channels are utilized

  -   For a 14' partition wall, four 6' grill channels and two  21.5" channels are 

utilized.

 

NoTE: Wall sections that span over 12’ long will require a 4” 

x 4” center support post.

   -  Install the 6' channel first by butting it flush with the face of the post. Install 

the second channel for the appropriate distance. It may be necessary to 

cut this component. Then attach channels with the screws provided.

STEP 7

At a height 36 3/8" install two 7" header U-channels above the top of the 46

"

 

U-channel.

 

STEP 8 

Place the 2” x 10” header board in the 7” U-channels allowing it to extend 1/2” 

below the 7” U-channels. Use a screw at each end to hold the header board 

in place for now. Put the top grill channel in position on the bottom of the 

header board again hold in place with screws.

STEP 9

Insert  the  grill  bars  starting  at  one  end.  Place  the  grill  bars  in  the  top  grill 

channel then lower into the bottom grill channels, repeat until all bars are in 

place. When all bars are in place, remove the screws used to hold the header 

board and top grill channel. Push or pull down on the header board until it 

seats evenly on the top of the grill bars. Now secure the header and top grill 

channel in place with the screws provided.

STEP 10

Install the two wall braces, 46" for grilled walls or 94 1/2” for solid walls, 

placing one on each side of the wall opposite each other and centred in the 

partition.

 

FEED DOOR STYLES

Hinge

Point

Pull down

& open

Hinge

Point

Swing-Out Feed 

Door Installation

1.  First decide where you want the 

swing-out feed door located.

2.  omit 7 bars from the grill section 

(Stay at least one bar from either 
end of the grill section)

3.  The swing-out feed door comes 

completely assembled and ready 
for installation and is installed in 
the same way as the grill bars.

Feed Opening
Installation

1.  First decide where you want the feed 

opening.

2.  cut two bars to the desired length, 22” 

long bars will leave approximately a 12” 
opening.

3.  Slide feed opening over the two outer 

bars of the opening. Let the feed opening 
plate rest on the bottom grill channel. 
Insert the two cut bars in the top grill 
channel and slide the feed opening up 
until it is tight with the two bars. Use the 
self-drilling self-tapping screws to hold 
the feed opening plate in place. Note: 
Screw through feed opening plates into 
the outer bars of the opening. Place 
screw at all four corners as shown.

FLIP DOWN V-DOOR

FliDr

V-Door
Installation

The V-Door grill section is delivered pre-

1. 

assembled as one-piece
Follow the Stall Door Assembly steps as 

2. 

outlined on page 7 with Step 3 omitted

V-Door not exactly as shown.

Summary of Contents for Rockwood Stall Series

Page 1: ......

Page 2: ...ng as desired on center to fit building design or special needs The Grill length See c in fig A of a standard 10 stall front is 65 and 91 for a 12 stall front See Fig A However grill sections can be c...

Page 3: ...ary lumber to a length 1 4 to 3 8 less than the distance measured between the inside faces of the U channel STEP 3 Installing the lumber in the U channels 3a Slide the first board down to the bottom o...

Page 4: ...x 2 1 2 L a g S p r i n g P l a s t i c W a s h e r...

Page 5: ...all Front 91 grill Top door track facemount brackets Offset track bracket Grill Rods 3 8 X 2 1 2 Lag bolts 5 16 X 1 1 2 Lag bolts ide nnel ottom nnel p nnel nsert g 7 r detail p Continuous top bracing...

Page 6: ...ight 36 3 8 install two 7 header U channels above the top of the 46 U channel STEP 8 Place the 2 x 10 header board in the 7 U channels allowing it to extend 1 2 below the 7 U channels Use a screw at e...

Page 7: ...to pages 4 8 for the installation of the door trolley assembly and door latch completing these steps at this time will make it much easier STEP 9 Position and secure in place the two pre assembled doo...

Page 8: ...sembly in the approximate center of the door between the door side U channels STEP 10 Now insert the grill bars starting at one side until all bars are in position Then secure the center grill assembl...

Page 9: ...ch stall door post and mark a horizontal line across each post With help lift your track so that the top of each facemount bracket lines up with corresponding line Attach the brackets with 1 lag bolt...

Reviews: