INSTALLATION PREPARATION
The fireplace is shipped with all gas controls and components installed and pre-wired. Before installing the fireplace, follow
these steps:
1.
Remove the shipping carton, and retain the front of the carton (used to protect the fireplace during construction).
2.
Remove the shipping pad, exposing the front glass door.
3.
Remove the glass door
(
Page 61
)
.
NOTE:
Barrier must be removed to remove the door. Barrier must be protected from damage and construction dust and dirt.
NOTE:
Place the glass door on the shipping carton to protect its surface
.
INSTALLATION SEQUENCE
The typical sequence of installation is outlined below; however, each installation is unique and may result in variations to the
steps described.
See the pages referenced in the following steps for detailed instructions.
Check local codes for more restrictive installation. The more restrictive installation for clearances must be used.
Framing
1. Construct the Fireplace Framing
(
Page 17
)
.
2. Prepare the Fireplace Top Spacers
(
Page 21
)
.
3. Installing Non-Combustible Front Fireboard Standoff
(
Page 21
)
.
4. Route the Gas Supply Line to the Fireplace
(
Page 21
)
.
5. Installing Header Shield
(
Page 22
)
.
6. Rough in the Electrical Supply, if Needed
(
Page 22
)
.
7. Place the Fireplace in the Framing and Secure
(
Page 23
)
.
Venting
8. Select a Horizontal or Vertical Vent System
(
Page 23
)
.
9. Install the Vent Restrictor (if necessary)
(
Page 23
)
.
10. Connecting the Vent Pipe
(
Page 25
)
.
11. Install the Vent System
(
Page 28
)
.
Electrical Connection
12. Complete the Field Wiring
(
Page 41
)
.
Gas Connection
13. Connect the Gas Line
(
Page 44
)
.
14. Verify Proper Fireplace Operation
(
Page 45
)
.
Finishing
15. Initializing the Remote Control System
(
Page 46
)
.
16. Install the Porcelain Liners
(
Page 47
)
.
17. Install the Glass Media
(
Page 47
)
.
18. Install Interior Options
(
Page 47
)
(see Accessory Components Page 64) -
(follow instructions included with optional accessories)
19. Install the Glass Door
(
Page 47
)
.
20. Adjust the Air Shutter to Ensure Proper Flame Appearance
(
Page 47
)
.
21. Install the Hood
(
Page 49
)
.
22. Re-installation of the barrier assembly
(
Page 49
)
.
23. Installation / replacement of blower
(
Page 49
)
.
24. Installation/Re-installation of the barrier assembly
(
Page 50
)
.
25. Install the Finishing Materials
(
Page 50
)
.
26. Attach the Safety-in-Operation Warning Labels
(
Page 50
)
.
1.
Construct the Fireplace Framing
1.
Frame the fireplace as illustrated in
Table 10, Page 18
. All framing details must allow for a minimum clearance to combustible framing
members as shown in
Table 8, Page 15
.
2.
If the fireplace is to be elevated above floor level, a solid continuous platform must be constructed below the fireplace.
NOTE:
Headers may be in direct contact with the fireplace top standoff spacers when they are bent up vertically, maintaining the 4”
clearance to the fireplace top, but must not be supported by them or notched to fit around them. All construction above the fireplace
must be self-supporting. DO NOT use the fireplace for structural support.