SG2K5TL/SG3KTL/SG4KTL-31
User Manual
28
Scenario 1:
Several inverters are operated in parallel connection to the single-phase
Low Voltage grid.
Requirements:
The sum of all inverters in parallel connection is limited to
THIRTY
.
Scenario 2:
Several inverters are operated in parallel connection to the three-phase
Low Voltage grid.
Requirements:
z
The sum of all inverters in parallel connection is limited to thirty.
n(L1)+n(L2)+n(L3)
≤
30.
z
Inverters should be distributed as equally as possible between the three phases
with maximum unbalanced load of 4.6kVA.
Scenario 3:
Several inverters are operated in parallel connection to low-voltage side
of MV transformer. The high-voltage side of MV transformer is connected to the
Middle Voltage Grid.
Summary of Contents for SG2K5TL
Page 2: ......
Page 6: ......
Page 10: ...IV...
Page 16: ...SG2K5TL SG3KTL SG4KTL 31 User Manual 6...
Page 60: ...SG2K5TL SG3KTL SG4KTL 31 User Manual 50 10 3 Overview of Complete LCD Menu Fig 10 1 Menu Tree...
Page 76: ...66 Temperature Derating Curve 1 0 2 45 60 Pnom P U Ambient temperature C...
Page 79: ......