7 Commissioning
7.1
Safety Instructions
High voltage! Electric shock!
Wear proper protection equipment before all operations on the device.
Do not touch the live terminals or conductors.
Respect all safety instructions inside the device and in this manual.
Respect all safety instructions prescribed by the manufacturer of devices
connected to the MV Station.
Grid-connection of the MV Station can be done only after receiving approval from
the local utility grid company and by qualified personnel.
After the MV Station is operating, make sure there are no flammable materials at
least 5 meters around the installation site.
Local/national standards about the min. electric clearance around the MV Station
should be respected.
Make sure the installation is correct and no spare parts or tools are left inside the
device.
Close the doors of the MV Station and the internal devices if the commissioning
process is stopped.
7.2
Requirements for Commissioning
Before commissioning, installations inside the MV Station should be checked thoroughly.
Ensure all the cable connections are secure and all bolts are fixed properly.
Ensure DC side voltage meets MV Station requirements and the polarity is correct.
Ensure AC side voltage meets MV Station requirements.
Ensure all cable connections meets related standards and requirements.