10 Operation of LCD Display Panel
User Manual
64
10.3
Main Screen
If the inverter succeeds in commissioning, LCD display will enter into the main
screen, as shown in Fig. 10-2.
Fig. 10-2
Main Screen Description
No.
Description
1
Power curve. x-axis: time in hours; y-axis: output power yield P in %.
2
Icons (refer to the Tab. 10-3) and the Inverter active power limits (P-W limits).
3
Current output power.
4
Energy generation during this day until now.
5
Total energy generation since initial commissioning.
6 Inverter
state.
7
Date (year/month/date) and time.
The energy yields displayed by the LCD panel are indicative only.
For the actual yields, please refer to the electric energy meter.
Tab. 10-2
Inverter State Description
Inverter State
Description
Run
After being energized, the inverter tracks the PV arrays’ maximum
power point (MPP) and feeds AC power to grid. This mode is the
normal mode.
Standby
Inverter will enter into Standby mode for insufficient input power.
In this mode the inverter will wait until the DC voltage recovers.
Stop
The inverter is shut down.
Key-stop
The inverter will stop operation by manual “Stop” through LCD
menu.
Start
…
The inverter is initializing and synchronizing with the grid.
Upd fail
IAP update fails
Summary of Contents for SG10KTL
Page 2: ......