Operation and control
V 152 10 11
Rev.: END
5-1
5
Operation and control
Each person who is involved in the operation, maintenance and repairing of the
gantry press must have carefully read and understood these operating instructions
before starting work.
5.1
General information
Work on the gantry press may be performed by trained and/ or instructed personnel
only. If not used as intended, this may be hazardous for life and limb, the gantry press
and connected systems, and the efficient operation of the gantry press. The
equipment may be used only for the purpose which the manufacturer specified or
which is standard.
The gantry press may be operated by authorised, technically proficient persons only.
A technically proficient person can assess and perform the work given to him and
recognise potential hazards based on his technical education, knowledge and
professional experience as well as knowledge of the accident prevention and
industrial safety regulations, provided he also satisfies the required personal
prerequisites for the activity, e.g. he can work independently. To avoid accidents, the
gantry press may be operated when in a technically perfect condition only. Third-party
components must not be used on the gantry press, otherwise the required safety
compliance cannot be guaranteed.
Do not use any working habits that may impair safety on the gantry press. The
operator must immediately notify the relevant supervisor of any changes made to the
gantry press (which compromise safety). The operator must immediately shutdown
the gantry press if a malfunction impairs the safety of the employees. The gantry
press must not be restarted until the malfunction has been eliminated. Safety
equipment must not be removed or manipulated or shut down.
The plant operator shall ensure that the function of the safety equipment on the
gantry press is checked both before the first start-up and before each subsequent
restart. These checks must be performed by instructed personnel.
The plant operator shall provide the operating personnel with the required personal
protective equipment (PSA) and also ensures that it is used.
No covers on drive components may be removed before the dangerous movements
have stopped and must be properly attached before the machine is restarted.
Summary of Contents for Plus 70
Page 58: ...Appendix V 152 10 11 Rev END 8 2 8 1 Declaration of Conformity...
Page 59: ...Appendix V 152 10 11 Rev END 8 3 8 2 Assembly drawings...
Page 60: ...Appendix V 152 10 11 Rev END 8 4 8 3 Parts list with recommended identified spare parts...
Page 61: ...Appendix V 152 10 11 Rev END 8 5 8 4 Hydraulic diagram parts list...
Page 62: ...Appendix V 152 10 11 Rev END 8 6 8 5 Circuit diagram parts list...
Page 63: ...Appendix V 152 10 11 Rev END 8 7 8 6 Supplier documentation...