Check that the tractor’s ‘permissible carried weight’ and the ‘rear overhang allowed’
are compatible with the weight and dimensions of the fully loaded sprayer and complete
with equipment mounted for the treatment.
The tractor’s power take-off (PTO), under all utilisation conditions, must provide a power
exceeding that absorbed by the sprayer.
The hitching has to be carried out on a plane surface with a suitable consistency, after
having checked that all the people not involved with the operation moved away, as well
as the children and the animals possibly present. The road circulation is exclusively
allowed in full observation of the rules in force in the country where the machine is to be
used, WITHOUT having loaded any chemical substances inside the tank.
12
COUPLING MODALITIES
EXECUTION
1. Loosen the chains of the lifter arms.
2. Start the tractor and take the lifter’s arms to the level of the machine’s pins.
4. Insert the toggle joints on the machine’s pegs, locking them with the clip pins.
5. Hook the 3rd-point rod from the tractor to the machine and securing it with the peg and the clip pin.
6. Screw the rod to set it into tension.
7. Start the tractor and hoist the sprayer until the 2 PTO are the same height.
Stop the tractor and remove the key from the control panel.
3.
8.
Stop the tractor, remove the key from the control panel and make sure that no
one approaches the hydraulic controls of the lifter.
NEVER OPERATE OR STAND BENEATH THE MACHINE OR IN THE AREA THAT
COULD BE INVOLVED IN ITS SUDDEN LOWERING.
9. By acting on the 3rd-point rod, vertically align the sprayer. N.B.: block the 3rd-point rod with the
specific lock ring.
10. Block the coupling by tightening the chains of the hoister arms.
When the operation is completed the 2 drive outlets (PTO) must be positioned on the same
axis, both in vertical and horizontal direction.
ST101-GEO-i 400 / 600 LITER