System - Vertical Votator II
The Gravity Refrigeration System includes the following items
that must be installed:
•
Accumulator
•
Media piping
•
Valves
The accumulator, refrigeration piping, and valves are shipped
loose for field installation, as shown in the drawing titled Vertical
Refrigeration System located in the addendum section and
Votator II Vertical Refrigeration System drawing on page 18
showing the Process Flow Diagram of the Vertical Refrigeration
System. It is necessary for on-site installation of these
components to insure that the refrigeration system will mate
properly with the Votator II cylinders.
A crane, or other lift device, is needed to lift the accumulator
mounting bracket in place for installation. Lift the mounting
bracket in place with a sling. Bolt the accumulator to the pole.
To simplify installation, piping is provided in three modules:
•
the accumulator to the lower manifold
•
the lower manifold to the cylinder flange
•
the upper manifold to the accumulator
Also included are an elbow for the top of the accumulator and
piping legs for connecting the modules.
The refrigeration valves and level control are packed and shipped
separately. These components and the piping sections should be
installed in accordance with the referenced drawings. A leak test
MUST be performed after all welding is complete.
After a leak test has been successfully completed, the system
piping should be coated with a paint formulated for corrosion
resistance.