Load priority
:
load>battery>GRID
When the photovoltaic energy is enough, first supply power to the
load, then charge the battery, and finally exported to the grid.
Power priority
:PV>battery>GRID
When the load power is too large, first from the photovoltaic
energy, and then battery discharge, and finally consume the
power from the grid.
1
)
In the morning, the photovoltaic
energy is insufficient, and the
load is powered by PV, battery
and the grid.
2
)
In the afternoon, the photovoltaic
energy is sufficient, the load is
powered by photovoltaic, the
battery is charged, and finally
exported to the grid.
Morning
PV
BAT
EPS
AC
Afternoon
PV
BAT
EPS
AC