Solax X3 series User Manual Download Page 10

5.3 Installation Precaution

Please avoide direct sunlight, rain exposure, snow laying up during installing and 
operating.

Available Space Size

X3 Series inverter is designed for outdoor installation (IP 65).
Make sure the installation site meets the following conditions:
   Not in direct sunlight.
   Not in areas where highly flammable materials are stored.
   Not in potential explosive areas.
   Not in the cool air directly.
   Not near the television antenna or antenna cable.
   Not higher than altitude of about 2000m above sea level.
   Not in environment of precipitation or humidity
   Be sure the ventilation is good enough.
   The ambient temperature in the range of -25

 to +60

.

   The slope of the wall should be within 

±

5

°

.

Position

Min.size

Ø

30cm

30cm

Left

30cm
30cm
30cm
30cm
30cm

Right
Top
Bottom
Front

Table Available Space Size

30cm

30cm

5.4 Installation Steps

Preparation

Step 1: Screw the wall bracket on the wall 

Step 2: Match the inverter with wall bracket

Ø

Ø

Ø

Below tools are needed before installation.

Installation tools : crimping pliers for binding post and RJ 45, screwdriver, 
stripping pliers,wire crimpermanual wrench and

 φ

10

 

drill

.

  

a)

  Use the wall bracket as a template to mark the position of the 4 

holes on the wall.

b) 

 Drill holes with driller, make sure the holes are deep enough (at 

least 60mm) for installation,  and then tighten the expansion tubes.

c) 

 Install the expansion tubes in the holes, and tighten them. Then 

install the wall bracket by using the expansion screws.

d) 

 Hang the inverter over the bracket, move the inverter close to it, 

slightly lay down the inverter, and make sure the 4 mounting bars on the 
back are fixed well with the 4 grooves on the bracket.

a)

b)

 

16

17

Installation 

Installation 

The wall hanging the inverter should meet conditions below:
1.solid brick/concrete, or strength equivalent mounting surface;
2.Inverter must be supported or strengthened if the wall’s strength isn’t 
enough(such as wooden wall, the wall covered by thick layer of decoration)

Summary of Contents for X3 series

Page 1: ...ual belongs to Solax Power Network Technology Zhe jiang Co Ltd Any corporation or individual should not plagiarize partially or fully copy including software etc and no reproduction or distribution of...

Page 2: ...ter 3 3 Dimension 4 Technical Data 4 1 DC Input 4 2 AC Output 4 3 Efficiency Safety and Protection 4 4 General Data 5 Installation 5 1 Check for Transport Damage 5 2 Packing List 5 3 Installation Prec...

Page 3: ...rmation appear in this document as described below Danger Danger indicates a hazardous situation which if not avoided will result in death or serious injury Warning Warning indicates a hazardous situa...

Page 4: ...nd of the DC cabling and at the array located between the inverter and the PV generator if the voltage protection level VP of the surge arresters is greater than 1100V an additional SPD type 3 require...

Page 5: ...tion and that wire is not undersized Do not disassemble any parts of inverter which are not mentioned in installation guide It contains no user serviceable parts See Warranty for instructions on obtai...

Page 6: ...all comply with the requirements of BS 7671 Electrical installation of PV system shall comply with requirements of BS 7671 and IEC 60364 7 712 No protection settings can be altered User shall ensure t...

Page 7: ...configuring system correctly including using the specified wires The system must be installed only by professional assemblers who are familiar with requirements for safety and EMC The assembler is re...

Page 8: ...t power factor Feed in phase 8000 8800 11 6 12 8 Object A DC Switch optional Pocket WiFi Lan GPRS all optional DRM Smart plug optional AC Connector B C D E F G H I J Description Waterproof plug RS 485...

Page 9: ...w MAINS PV Forced air ow 45dB WIFI optional Lan optional GPRS optional Meter optional USB DRM RS485 5 10 optional 5 Installation 5 1 Check for Transport Damage 5 2 Packing List Make sure the inverter...

Page 10: ...cket on the wall Step 2 Match the inverter with wall bracket Below tools are needed before installation Installation tools crimping pliers for binding post and RJ 45 screwdriver stripping pliers wire...

Page 11: ...N X3 15 0P T N is purchased X3 8 0P T N X3 8 0P T D X3 10 0P T N X3 10 0P T D X3 12 0P T N X3 12 0P T D X3 15 0P T N X3 15 0P T D Danger Danger to life due to high voltage on DC conductors when expose...

Page 12: ...8mm The parameters have some differences because of different environment and material Please according to the local conditions to choose appropriate cable and micro breaker X3 8 0P T N X3 8 0P T D X3...

Page 13: ...d in the end use system connectors cables junction box switch ger etc and the reverse current PV modules shall be considered based on the feedback current and reverse current The direct current DC cir...

Page 14: ...onal three phase meter Load X3 series inverter 1 Prepare RJ45 connector and a communication cable 2 Trip the insulation from the communication cable 3 Let the communication cable pass though the water...

Page 15: ...DSP 618 00103 00_MIC_DSP_Vx xx_xxxxxxxx hex Upgrade Steps Update ARM DSP 3 then insert U disk into the USB port on the bottom of the inverter Then turn on DC switch or connect the PV connector the LCD...

Page 16: ...time to start up Above steps are for the regular start of the inverter If it is the first time to start up the inverter you need to setup the inverter 6 Operation Method 6 1 Control panel Below is the...

Page 17: ...nterface User can select interface by moving the cursor with function button and press OK to confirm Status The status function contains three aspects of the inverter grid solar and load Press up and...

Page 18: ...y country VDE4105 Load L1 Power 0W Setting If inputting the installer password the information of the LCD interface is as below a Safety The user can set the safety standard here According to differen...

Page 19: ...r down button Press OK to confirm and alternate to next word After word is confirmed press OK to reset the password New Password 1 2 3 4 34 35 Operation Method Operation Method e RF Control RF Control...

Page 20: ...ive standard curve cos f P For VDE ARN 4105 curve cos f P should refer to curve A default values of setting are as shown in curve A For E 8001 curve cos f P should refer to curve B default values of s...

Page 21: ...nd press OK to confirm the selection press ESC to return to Menu a Inverter Yield The inverter yield function contains energy generated by today yesterday this month last month and total Press up and...

Page 22: ...nnect them Or seek help form us if can not go back to normal state PV connection setting fault Disconnect PV and PV reconnect them Or seek help form us if can not go back to normal state EEPROM readin...

Page 23: ...n shall examine and maintain the machine regularly The concrete operations are follow 1 Check that if the cooling fins on the rear of house are covered by dirts and the machine should be cleaned and a...

Page 24: ...owing requirements Suitable for loads more than 30 kg With handle Can be fully closed 8 3 Storage and Transportation Store the inverter in dry place where ambient temperatures are always between 25 C...