To install the current transformers (CTs):
NOTE
If installing a high-accuracy/RGM meter, make sure
that the CTs chosen are appropriate for use with the
meter.
1. Turn off AC power before clamping on current transformers.
2. Install the CTs around the conductor to be measured. Split-
core CTs can be opened for installation around a
conductor. A nylon cable tie may be secured around the CT
to prevent accidental opening.
3. Install the CTs with the arrows pointing to the grid for
consumption or export measurement.
Energy Meter with Modbus Connection Installation Guide MAN-01-00269-1.5
Chapter 2: Meter Installation
19