EH-1200F Installation Manual
Page 51
4
Commissioning and Acceptance Procedure
This chapter presents the recommended commissioning and acceptance procedure to
be performed following the installation of each EtherHaul radio link.
The commissioning and acceptance procedure verifies the correct installation and the
proper, safe, and robust operation of the EtherHaul RF link.
This chapter includes the following topics:
Installation Verification and Testing
EtherHaul Commissioning and Acceptance Form
4.1
Installation Verification and Testing
Inspect the following components and confirm their adherence to requirements that are
detailed in the accompanying checklist.
4.1.1
Physical Installation Verification
This inspection verifies the physical installation of the ODU, in accordance with the
EtherHaul’s installation procedure and requirements.
1.
Pole mount installation
2.
ODU installation
3.
Weatherproofing the cables
4.
Cables installation
5.
Grounding
4.1.2
RF Link Test
This inspection verifies the RF link status.
1.
RF LED is green.
2.
Management/CLI indication: “RF Operational – Up”.
3.
Receive Signal Strength Indication (RSSI) achieved in Alignment mode is within
+/-4dB of the expected value.
4.
Carrier to Interf Noise Ratio (CINR) is 19 or higher.
5.
Highest modulation achieved
6.
Link configuration is in accordance with plan requirements.
4.1.3
Link Errors Test
This inspection verifies frame-loss-free operation of the radio link.