Commissioning
Instruction Manual AquaScat S
13798E/3
49
6.2
Commissioning with SICON (M)
Proceed with the initial start-up in accordance with the following table:
WORKSTEP
ADDITIONAL INFO / IMAGES
1.
Ensure that the photometer and control unit
are correctly mounted and connected.
2.
2.1: Establish the service voltage.
The welcome screen appears on the display.
The factory setting language is English.
Accordingly, the displayed language during the
initial start-up is English.
2.2: The instrument carries out an internal
functional check.
2.3: The instrument is ready for measurement.
3.
Set the language.
Section 8.1
4.
Set the current outputs.
Section 8.2
5.
Set the limits.
Section 8.3
6.
Set the outputs.
Section 8.4
7.
If an optional Profibus module is present, set
the Profibus parameters.
Section 8.5
8.
If an optional Profinet IO module is present, set
the Profinet parameters.
Section 8.6
9.
If an optional Modbus module is present, set
the Modbus parameters.
Section 8.7
10. Set the date and time.
Section 8.8
11. Enter the access code.
Section 8.9
12. Carry out recalibration.
Section 9.6
13. Back up the configured data.
Section 8.10