Chapter 2
Installing the Device
RUGGEDCOM MX5000
Installation Guide
8
General Procedure
•
Section 2.6, “Connecting the Failsafe Alarm Relay”
•
Section 2.7, “Connecting Power”
Section 2.1
General Procedure
The general procedure for installing the device is as follows:
1. Review the relevant certification information for any regulatory requirements. For more information, refer to
2. Review the
RUGGEDCOM MX5000 Modules Catalog
for special installation or regulatory requirements related
to the modules installed in the device.
3. Mount the device.
4. Connect the failsafe alarm relay.
5. Connect power to the device and ground the device to safety Earth.
6. Connect the device to the network.
7. Configure the device.
Section 2.2
Unpacking the Device
When unpacking the device, do the following:
1. Inspect the package for damage before opening it.
2. Visually inspect each item in the package for any physical damage.
3. Verify all items are included.
IMPORTANT!
If any item is missing or damaged, contact Siemens for assistance.
Section 2.3
Mounting the Device
The RUGGEDCOM MX5000 is designed for maximum mounting and display flexibility. It can be equipped with
adapters that allow it to be installed in a 48 cm (19 in) rack or directly on a panel.
IMPORTANT!
Heat generated by the device is channeled outwards from the enclosure. As such, it is recommended
that 2.5 cm (1 in) of space be maintained on all open sides of the device to allow for some
convectional airflow.
Forced airflow is not required. However, any increase in airflow will result in a reduction of ambient
temperature and improve the long-term reliability of all equipment mounted in the rack space.