Appendix
A.4 Acceptance test/configuration test
Power Module PM330
Hardware Installation Manual, 12/2018, A5E32844552B AF
135
A.4.1
Acceptance test STO
Table A- 4
Procedure for the STO acceptance test
Status
1. The inverter is ready for operation
•
The inverter signals neither faults nor alarms.
•
STO is not active (
r0002 ≠ 44).
(e.g. R0002 = [31] Ready for switching on – set "ON/OFF1" = "1/0" (p0840)
2. Switch on the motor
2.1. Enter a speed setpoint
≠
0.
2.2. Switch on the motor (ON command).
2.3. Check that the correct motor is running.
2.4. Check the status of the safety relay LEDs
(here in the example, a 3SK1112-… or 3SK112x-…)
•
LED (1) DEVICE = green
•
LED (2) OUT = green-> 3SK1 output circuit closed
•
LED (3) IN = green-> 3SK1 switch-on (close) conditions satisfied
–
Input circuit closed
–
Feedback circuit closed
–
Start button where necessary actuated
•
LED (4) SF = OFF
Summary of Contents for PM330
Page 1: ......
Page 2: ......
Page 8: ...Table of contents Power Module PM330 6 Hardware Installation Manual 12 2018 A5E32844552B AF ...
Page 20: ...Introduction Power Module PM330 18 Hardware Installation Manual 12 2018 A5E32844552B AF ...
Page 149: ......
Page 150: ......