Final Work Steps
ARCADIS Avantic
SPR2-330.815.01.03.02
Siemens AG
12.06
CS PS SP
Page 50 of 66
Medical Solutions
•
Mark the following rows in the "Device leakage current" protocol, column "First mea-
sured value", with "n.a." as "not applicable":
¹
Row "Meas. inst. calibrated up to:"
¹
Row "Evaluation:"
•
Complete the following rows in the "Device leakage current" protocol, column "First
measured value":
¹
In the row "Date:" enter the current date.
¹
In the "Name" row, enter your name in block letters.
¹
Sign the protocol in the "Signature" row.
•
If you want to complete the protocol with additional remarks, enter them in the
"Remarks" table in the protocol addendum.
Device leakage current measurement during start-up (if necessary)
NOTE
If the programmed line voltage has been changed from its status
at delivery, and/or there have been changes of parts in the sys-
tem's primary circuit, the device leakage current value specified
in test protocol 1 delivered with the system is no longer valid.
The device leakage current measurement has to be performed.
NOTE
Observe the leakage current measurement instructions in the
"General Information" chapter of these instructions.
WARNING
Electrical voltage!
Non-compliance can lead to severe injury and even death.
¹
The system leakage current measurement may be per-
formed on systems of protection class I only after the
protective conductor test has been passed.
•
Perform the device leakage current measurement after successfully completing the
protective conductor test.
•
Complete the "First measured value" column of the "Device leakage current" protocol.
•
If you want to complete the protocol with additional remarks, enter them in the
"Remarks" table in the protocol addendum.