MSCDN – MP2A Commissioning
INSTRUMENT DESCRIPTION
[ R1 METERS ]
--> press down <--
Start of resistor 1 meters
R1 Nom Currents
0.00 0.00 0.00 xIn
Resistor 1 secondary nominal currents
(A,B,C xIn)
[ R2 METERS ]
--> press down <--
Start of resistor 2 meters
R2 Nom Currents
0.00 0.00 0.00 xIn
Resistor 2 secondary nominal currents
(A,B,C xIn)
[ OPEN CCT METERS ]
--> press down <--
Start of resistor open circuit meters
Open Cct Currents
0.00 0.00 0.00 xIn
Resistor open circuit nominal currents
(A,B,C xIn)
Lower resistor R1 one phase A current until operation occurs and record results below. Raise until R1 phase A
current equals R2 phase A current and element resets. Repeat with phases B and C verifying that the LED
indication is as expected in each case.
Repeat for resistor R2.
RESISTOR A
B
C
R1
R2
Return all settings to those to be used, and reset the thermal capacity.
9 Primary Injection Tests
Primary injection tests are required to prove the CT ratio and secondary connections to the relay. A polarity test is
NOT required for this relay.
Inject using a primary injection test set and record and verify the expected levels on the instruments on the relay.
RESISTOR Ia
Primary
Injection
Ia Relay
Instruments
Ib Primary
Injection
Ib Relay
Instruments
Ic Primary
Injection
Ic Relay
Instruments
R1
R2
10 Tripping And Intertripping Tests
Re-connect the auxiliary d.c. supplies for trip and alarm operations and insert the Trip and InterTrip links.
Simulate the operation of each external contact that initiates a status input and in each case check that
appropriate LED illuminates and that the correct tripping, intertripping and alarm initiation occurs.
Disconnect the d.c. power supply to the MSCDN-MP2A relay and check for correct PROTECTION
INOPERATIVE alarm. Operate the thermal protection and the open circuit protections in turn by primary or
secondary injection and check that the correct tripping, indication occurs.
11 Putting Into Service
Ensure that: The trip supply is connected.
All the RED LEDs are off
The GREEN LED is ON steady.
Ensure that all earth links, trip links and inter-trip links are in their normal operational positions.
Ensure that the thermal states of the resistor thermal protections are reset