COMMISSIONING
7
Commissioning
7.1
Quick commissioning (with factory settings)
General requirements
−
Installation according to reference conditions (safety distances, etc.)
−
Can only be used if installed using G3/4" A or 3/4
"
NPT process connection
Quick commissioning
1.
Mount the sensor as appropriate to the installation conditions, see
2. Adapt the level so that approximately 50% of the probe is covered with the measur-
ing medium.
3. Automatically adjust the medium.
•
Adjust using AUTCAL.
This menu can be accessed via EXPRT and USER.
•
The successful AUTCAL
function is confirmed with
!CALOK.
4.
Configure outputs, see
“8.3 Configuring the switching outputs”.
Note:
The following parameters are automatically adjusted while executing the AUTCAL func-
tion:
• The EXPRT / MEAS / TRSHLD parameter is adjusted.
• The EXPRT / MEAS / ADAPT = 60 s parameter is adjusted.
Note:
If the AUTCAL
function was confirmed with
!FAILD
, relaunch commissioning.
In the event of problems during commissioning, see
.
7.2
Commissioning
Advanced commissioning must always be performed if the required measurement
performance is not achieved after quick commissioning. This may be the case if, for
example, media with very low DC values (e.g., silicone oils) are to be measured.
Advanced commissioning must also be performed during assembly with an Easy Clamp
bracket.
General requirements
−
Installation according to reference conditions (safety distances, etc.)
−
Installation using G3/4" A or 3/4
"
NPT process connection
−
Installation using Easy Clamp