DU/SD SERIES INSTALL OPERATION MAINTENANCE MANUAL
|
45
APPENDIX D: COMMISSIONING REPORT
Unit Details
Pass =
Adjust = A
Attention Req. = X
Model Number
Serial Number
Installer
Installation Date
Site Address
Unit Condition
General Installation
Access to the Unit
Condition of Casing
Unit is adequately secured
Structural bolts and grub screws tight
Roof Stand Installation
Duct Work to unit connected
Flue Installation
Electrical Commissioning
Have Electrical connections been completed by a licensed, experienced person
Isolator fitted and operating
Single or 3 phase power (test)
V
Fan Motor / Alignment (if fitted)
Pulleys/ Alignment (if fitted)
Fan Belts properly tensioned (if fitted)
Fan direction correct (if fitted)
Thermostat Connected/Operational
Gas Commissioning
Have Gas connections been completed by a licensed, experienced person?
Gas Isolation Fitted
Gas Supply free of condensate and deposits
Gas Train Connections
Pilot Connection
Incoming Line Purge
Incoming Gas Pressure
kPa
Gas Valve Converted for LPG
Correct Spuds Installed and Free of Obstructions
Visual Inspection of pipe work with leak detector
Modulating Motor Set and Operational Check
Controls
High Limit Control securely installed and free of damage
High Limit Temp as specified
High Limit Control Wired In
High Limit Control Trips when Heat Applied
Thermostat and Rotary Switch connected
BMS connection (if fitted)
Thermostat Range confirmed on RLU
Leaving Air Temp confirmed on RLU
Damper Blade Movement
General Operation
All Foreign Objects Removed from unit
All Access Panels Installed and Secure
De-isolate Gas Supply
De-isolate Electrical Supply
Heat on and Fan Low on Wall Switch begins ignition sequence
Pilot Ignition
Main Burner Ignition
Pilot Pressure
kPa
Main Burner Pressure
kPa
Temperature Rise Across Heat Exchanger
°C
Damper Position
Dampers Locked
Secure Location for Results communicated with owner