background image

25

I&O manual

8.7 Winter shutdown

For shutdown in winter, the surface of the unit outside and inside 
should be cleaned and dried. Cover the unit to prevent dust. Open 
discharge water valve to discharge the stored water in the clean 
water system to prevent freezing accident (it is preferable to inject 
antifreezer in the pipe).

8.8 Replacing parts

Parts to be replaced should be the ones provided by our company. 
Never replace any part with different part.

8.9 First startup after shutdown

The following preparations should be made for re-startup of unit 
after long-time shutdown:
1) Thoroughly check and clean the unit.
2) Clean water pipe system.
3) Check pump, control valve and other equipments of water pipe 
system.
4) Fix connections of all wires.
5) It is a must to electrify the machine 12 hours before startup.

8.10 Refrigeration system

Determine whether refrigerant is needed by checking the value of 
suction and discharge pressure and check whether there is a 
leakage. Air tight test must be made if there is a leakage or parts 
of refrigerating system is to be replaced. Take different measures 
in the following two different conditions from refrigerant injection.
1) Total leakage of refrigerant. In case of such situation, leakage 
detection must be made on the pressurized nitrogen used for the 
system. If repair welding is needed, welding cannot be made until 
all the gas in the system is discharged. Before injecting 
refrigerant, the whole refrigeration system must be completely dry 
and of vacuum pumping.

  Connect vacuum pumping pipe at the fluoride nozzle at 

low-pressure side.

  Remove air from the system pipe with vacuum pump. The 

vacuum pumping lasts for above 3 hours. Confirm that the 
indication pressure in dial gauge is within the specified scope.

  When the degree of vacuum is reached, inject refrigerant into 

the refrigeration system with refrigerant bottle. Appropriate amount 
of refrigerant for injection has been indicated on the nameplate 
and the table of main technical parameters. Refrigerant must be 
injected from the low pressure side of system.

  The injection amount of refrigerant will be affected by the 

ambient temperature. If the required amount has not been 
reached but no more injection can be done, make the chilled 
water circulate and start up the unit for injection. Make the low 
pressure switch temporarily short circuit if necessary.
2) Refrigerant supplement. Connect refrigerant injection bottle on 
the fluoride nozzle at low-pressure side and connect pressure 
gauge at low pressure side.

  Make chilled water circulate and start up unit, and make the low 

pressure control switch short circuit if necessary.

  Slowly inject refrigerant into the system and check suction and 

discharge pressure.

Maintenance of main parts

  Close attention should be paid to the discharge and suction 

pressure during the running process. Find out reasons and 
eliminate the failure if abnormality is found.

  Control and protect the equipment. See to it that no random 

adjustment be made on the set points on site.

  Regularly check whether the electric connection is loose, and 

whether there is bad contact at the contact point caused by 
oxidation and debris etc., and take timely measures if necessary. 
Frequently check the work voltage, current and phase balance.

  Check the reliability of the electric elements in time. Ineffective 

and unreliable elements should be replaced in time.

8.6 Removing scale

After long-time operation, calcium oxide or other minerals will be 
settled in the heat transfer surface of the water-side heat 
exchanger. These substances will affect the heat transfer 
performance when there is too much scale in the heat transfer 
surface and sequentially cause that electricity consumption 
increases and the discharge pressure is too high (or suction 
pressure too low). Organic acids such as formic acid, citric acid 
and acetic acid may be used to clean the scale. But in no way 
should cleaning agent containing fluoroacetic acid or fluoride 
should be used as the water-side heat exchange is made from 
stainless steel and is easy to be eroded to cause refrigerant 
leakage. Pay attention to the following aspects during the cleaning 
and scale-removing process: 

  Water-side heat exchanger should be done be professionals. 

Please contact the local air-conditioner customer service center.

  Clean the pipe and heat exchanger with clean water after 

cleaning agent is used. Conduct water treatment to prevent water 
system from being eroded or re-absorption of scale.

  In case of using cleaning agent, adjust the density of the agent, 

cleaning time and temperature according to the scale settlement 
condition.

  After pickling is completed, neutralization treatment needs to be 

done on the waste liquid. Contact relevant company for treating 
the treated waste liquid.

  Protection equipments (such as goggles, gloves, mask and 

shoes) must be used during the cleaning process to avoid 
breathing in or contacting the agent as the cleaning agent and 
neutralization agent is corrosive to eyes, skins and nasal mucosa.

8.5 Care and maintenance

Maintenance period 

It's recommended that before cooling in summer and heating in 
winter every year, consult local air conditioner customer service 
center to check and maintain the unit, to prevent air conditioner 
errors which bring inconvenience to your life and work. 

 Connection must be renewed after injection is completed.

 Never inject oxygen, acetylene or other flammable or poisonous 

gas to the refrigeration system at leakage detection and air tight 
test. Only pressurized nitrogen or refrigerant can be used.

CAUTION

Summary of Contents for SCV-xxEA

Page 1: ...AIR COOLED MODULAR CHILLER UNIT INSTALLATION AND USER MANUAL SCV xxEA AIR CONDITIONING...

Page 2: ...Original instructions...

Page 3: ...A Temperature testing components of total water outlet 1 1 1 1 Purpose Shape Qty Unit transformer Installation Operation Manual Use for installation only need for setting the main module Installation...

Page 4: ...2 SCV 600EA NO NAME 1 2 3 4 5 6 7 Air outlet Top cover Air inlet Electric control box Condenser Compressor Evaporator NO NAME 8 9 Water outlet Water intlet 1 2 8 7 9 4 6 3 5...

Page 5: ...matching and thus actually realizing optimal energy saving operation The product is Modularized unit and parallel connection of 16 modules can be realized at most so the user can adopt module combina...

Page 6: ...as unsorted municipal waste Collection of such waste separately for special treatment is necessary Keep far away from high frequency equipment Keep away from the following places a place where it is f...

Page 7: ...ticide Failure to observe could cause the chemicals to become deposited in the unit which could endanger the health of those who are hypersensitive to chemicals Do not place appliances which produce o...

Page 8: ...tend below frozen soil layer The foundation of the unit should not be connected to the foundation of the building to avoid affecting the people due to transfer of noise and vibration The base of the u...

Page 9: ...han the static pressure outside the fan The space between the unit and sunk fence or Persian blinds should also meet the requirement of the minimum installation space of the unit 3 3 1 3 If the unit n...

Page 10: ...n foundation of the unit unit mm 80 Cement mortar Concrete Drainage channel Fig 3 6 3 6 Installation of damping devices 3 6 1 Damping devices must be provided between the unit and its foundation By me...

Page 11: ...pes a All chilled water pipelines should be thoroughly flushed to be free of any impurity before the unit is operated Any impurity should not be flushed to or into the heat exchanger b Water must ente...

Page 12: ...eck valve Automatic discharge valve Symbol explanation Fig 4 1 Main unit Expansion tank Water replenishing Dirt discharge valve Differential pressure by pass valve Drain valve Two way valve Three way...

Page 13: ...tance pipe elbow and three way resistance two way resistance or three way resistance as well as filter resistance H4 the longest terminal resistance 4 7 2 Installation the pump a The pump should be in...

Page 14: ...ne must be consistent with the direction of arrow on the controller The connection terminal should be located where wiring connectioncan be easily done 4 9 4 Pay attention to the following items when...

Page 15: ...ngle module water system pipeline Fig 4 5 SCV 300EA Fig 4 6 SCV 600EA Water inlet Water outlet Total water outlet temperature sensor Electric control box Electric control box Water inlet Water outlet...

Page 16: ...items are determined The wired controller is 500m away from the outdoor unit 25 Q 50 50 Q 80 80 Q 130 135 Q 210 210 Q 325 325 Q 510 510 Q 740 740 Q 960 DN40 DN50 DN65 DN80 DN100 DN125 DN150 DN200 4 11...

Page 17: ...electromagnetic interference thus leading to failure of the unit and its controller and even damages to them 5 3 10 All weak current wires led to the electric box must apply shielded wires which must...

Page 18: ...d N Step 7 Phase sequences must be consistent when the wires of the main power Step 8 The main power should be located out of easy reach of non professional maintenance personnel to avoid mal operatio...

Page 19: ...hen the subordinate unit suffer fault of temperature sensor the unit will be shut down but other subordinate units will not be affected Taf1 Shell and tube low temperature ant freeze sensor1 fault cod...

Page 20: ...l modules stop operating 3 In case of shutdown under the pump mode the pump can be directly shut down CN30 Input of three phase four wire power supply fault code E1 Three phases A B and C of power sup...

Page 21: ...for the main unit Spot check The operating status of outdoor system can be observed through spot check and specific display contents are as shown in the following figure Display contents of operating...

Page 22: ...ed in Table 7 1 6 2 Check item table after installation Checking item Description Yes No Whether installing site is meet for requirements Whether water system is meeting for requirements Whether elect...

Page 23: ...ler must be connected according to electric control schematic diagram or the faults caused by water breaking while the unit is in operation should be the user s responsibility Do not re start the unit...

Page 24: ...ons 1 Plug and play system 2 RS 485 TS232 Standard serial communication port Turn on the unit Press MENU key to set the intended mode Power up to module unit and initially deliver power to wired contr...

Page 25: ...ir suction pressure Check ambient temperature around it Discharge the excessive refrigerant Charge sufficient refrigerant to the system Check fan rotating direction Reason about remove air short circu...

Page 26: ...re Replace a new compressor Replace damaged assembly Control circuit without power though Check the wring of control system Hi voltage or lo voltage protection Reference to mention in above the parts...

Page 27: ...2 error Communication error between main control board and wired controller Power phase sequence error P1 P0 1E0 E1 E2 E3 E4 E5 E7 E8 E9 1Eb 1Ed 2Ed 1P6 2P6 EC EF EH EP EU 2E0 3E0 P4 P5 P9 Condenser h...

Page 28: ...ll be a dynamic display of If the system is under OFF state there is no display c If the communication with the main unit Modular unit is fail it displays E2 d If it is under the host computer network...

Page 29: ...d check suction and discharge pressure Maintenance of main parts Close attention should be paid to the discharge and suction pressure during the running process Find out reasons and eliminate the fail...

Page 30: ...el connect the HEAT COOL port of the main unit s electric control box then connect the ON OFF signal provide by user to the HEAT COOL port of main unit as follows 0 electric control box ON OFF port ON...

Page 31: ...temperature of chilled water or hot water Inlet Outlet 6 check air temperature of air side heat exchanger Inlet Outlet 7 Check refrigerant suction temperature and superheating temperature Refrigerant...

Page 32: ...Outdoor temperature Compressor Air temperature of air side heat exchanger Temperature of chilled water or hot water Current of cooling water pump or hot water pump Dry bulb Wet bulb Indoor temperatur...

Page 33: ...etc High or low pressure switch freeze proof device water flow volume controller Overcurrent device power phase sequence device etc Standard heating input kW Heating rated current Notes the above dat...

Page 34: ...to water heat pump Brine to water heat pump For low temperature heat pumps parameters shall be declared for low temperature application Otherwise parameters shall be declared for medium temperature a...

Page 35: ...Kingdom 1 For heat pump space heaters and heat pump combination heaters the rated heat output Prated is equal to the design load for heating Pdesignh and the rated heat output of a supplementary heat...

Page 36: ...iary heater and pump is just for reference please follow the instructions of corresponding auxiliary heater products Please choose such accessory as power wire switch of auxiliary heater according to...

Page 37: ...iliary heater and pump is just for reference please follow the instructions of corresponding auxiliary heater products Please choose such accessory as power wire switch of auxiliary heater according t...

Page 38: ...unit is containing fluorinated gases included in the Kyoto protocol The maintenance and the liquidation must be carried out by qualified personnel Type of refrigerant R410A The composition of the cool...

Reviews: