S&C Instruction Sheet 1041-540 39
Updating Control Software
Occasionally, the operating system for the switch control or the control software may need
to be updated. The Update program, installed with IntelliLink software, easily replace
the old control software with the newer version.
Note:
The setpoint values and historical data stored in the switch control could be lost
during the update process. To be safe, always generate all needed reports using the old
IntelliLink and control software before updating the control.
NOTICE
S&C strongly recommends the switch control have ac control power (or sensor
power) as well as battery power during the update process .
If the control software must be updated while the control has battery power only,
the users
MUST follow the instructions described in the “Updating Control Software
With Battery Power Only” section on page 40 . Otherwise, the update process will
not run properly .
Complete the following steps to update the program:
STEP 1.
Install the contents of the new Setup disk on the computer.
For details, see “Start IntelliLink” section in Instruction Sheet 1041-530.
STEP 2.
Connect the computer to the Local Access port on the switch control.
STEP 3.
Start the Update program.
(a) In Windows, choose the
Start menu>Programs>EnergyLine>Update
process. The Update window appears. See Figure 11.
(b) Select the desired options, and then click on the
Start Update
button.
The Update Program
Note:
If the switch control is not connected to COM1 on the computer, click on the
Communication Setup
tab, select the correct comm port, click on the
Connect
button, return to the
Update Control Software
tab and click on the
Start Update
button.
Figure 11. The control software Update window.