Unpacking and Transporting
This paragraph describes the work to unpack cabinets and other components and
transport them to the place to be installed.
Bringing in Items
Bring in items, taking care of the followings:
When carrying a system, fasten the system firmly to the transport vehicle or
carrier to prevent damage to the system for a vibration or shock.
When carrying system, use a lift to prevent accidents. However, if the system
must be carried by people, enough people are required to carry the system.
Before moving the system, check the storage place for the system and remove
obstacles in advance.
While moving system, the system should not be shocked physically and
damaged caused by dust, moisture, and static electricity.
Unpacking Items
The procedure to unpack items is as follows:
The packing items must be packed until they reach the installation place.
The items are classified in accordance with each job specification and stored
on a place that does not interfere with working.
Unpacked systems must be installed immediately. If not installed immediately,
the systems must be stored in the installation place temporarily.
Unpack only external packing, leaving the internal packing in unpacked status.
Unpack the inner packaging after each system is placed on its installation
location.
Scrap by-products (packaging waste) in accordance with the rule. Do not
recycle the by-products.