2.
Make sure the emergency stop buttons are pushed in (off) and the remote cord toggle switch is in the
center (off) position.
3.
Use the recommended start settings chart to adjust machine for the type of insulation you are using and
particular operation. The material manufacturer’s instructions prevail since they guarantee the final results.
4.
Air flow rate may be controlled with the air bleed control valve
13
while monitoring system pressure on
the air gauge
14
. The system back pressure must be read while the
Volu-Matic 200
machine is operating
with full length and proper hose while material is being blown. Always start the adjustment with the air
bleed control valve in the fully closed position. See Fig. down below. If the air flow and pressure deliver
the desired results with the valve closed, then do nothing to the valve. As you begin to open the valve, air
is bled off from the exit of the blower preventing flow of all air to the airlock feeder. As you open the
valve, be careful to not open completely during open blow or the blowing hose could clog because of
insufficient air volume.
5.
To adjust the slide gate
15
, refer to the chart and select the proper setting for the material to be blown and
particular operation. Lift the handle
8
out of the notch and move to the left to open the slide gate. Place handle
in notch that matches with the desired setting on the scale
16
. The scale is calibrated in inches of opening.
CAUTION: As you open the valve, be careful not to open completely during open blow or the blowing
hose could clog because of insufficient air volume.
15
8
16
13
14
Summary of Contents for CertainTeed Volu-Matic 200
Page 12: ...12 Operation...
Page 22: ...22 Preventive Maintenance...
Page 28: ...28 Troubleshooting...
Page 32: ...32 Parts Drawings...
Page 33: ...33...
Page 34: ...34...
Page 50: ...50 Maintenance Record DATE JOB DESCRIPTION PERFORMED BY...