Chargepoint Installation Completion
EVZM-01-V01R1 Installation and Operation Manual
Zura Intelligent EV Charging Unit
December 2022
Page
36
of
42
Chargepoint Installation Completion
1. Make sure the…
x
Chargepoint is secured to the mounting location.
x
Chargepoint enclosure is free of debris.
x
Cables entering the chargepoint are secure.
2. Make sure the electrical installation is complete:
x
Incoming cables are connected to the relevant devices within the enclosure.
x
All electrical connection points are secure.
x
All required tests have been performed – in accordance with the current
legislation applicable in the geographical region of the installation.
x
Make sure the chargepoint has been installed in compliance with the current
Electrical Wiring Regulations (including recommended earthing arrangements).
CAUTION: Equipment Damage
Do NOT use power tools to remove/install panel fixings.
Use hand tools ONLY and do not overtighten fasteners.
3. Reconnect the RFID and the LED Indicator cables from the Rear Enclosure to the
Front Panel.
4. Fit the Front Panel of the enclosure taking care not to trap any electrical cables.
Secure the panel with the fixings removed earlier in the procedure.
x
Make sure the Front Panel is firmly and evenly secured to the Rear Enclosure.
x
Take care not to damage the fasteners or the plastic components.
5. Install the front fascia.
6. If required, remove any handling marks from the enclosure with a soft, damp cloth.
7. Make sure the service providers label(s) is neatly applied, close to the appropriate
socket or tethered cable.
8. If this installation is for a tethered chargepoint, install the charging plug holster(s).
9. Make sure this manual is given to the Owner/Host before leaving the site.