13. Place the Mounting Bracket onto
the wall.
14. Make sure the Mounting Bracket is
level and vertical.
15. For rear entry cabling, make sure
the power cable and any other
required cables will pass through
the large aperture in the lower area
of the bracket when it is secured to
the wall.
16. Use the holes of the bracket as
guide to mark where the bracket
will be secured to the wall.
x
The holes in the bracket provide
various fixing positions.
x
Where possible, use the furthest
apart positions.
Figure 30 Mounting Bracket Alignment
17. Drill appropriate holes in the wall for the fixings that will be used. If using the
supplied fixings, make each hole 55mm deep with an 8mm masonry drill.
18. Secure the bracket to the wall using the fixings provided or using alternatives
suitable for the location.
19. Make sure the bracket sits flush to the wall and is level when all fixings are
tightened.
20. Test fit the chargepoint onto the Mounting bracket and make sure there are no
fitting issues.
NOTE:
The installation can continue with the chargepoint mounted on the wall if this is
preferred. If the chargepoint remains mounted, secure it to the Mounting Bracket using
the fasteners removed at step 6. Alternatively, the chargepoint may be removed from
the mounting bracket before continuing.
NOTE:
All electrical work must be performed in accordance with the current legislation
applicable in the geographical region of the installation.
CAUTION; Equipment Damage – Sensitive Equipment
If you will be performing insulation resistance tests on the power supply cables, it is
advised to be done BEFORE connecting the cable to the chargepoint. The high
voltages applied during the test may damage sensitive components if tested after the
cable is connected.
21. If required, install the load balancing system. Refer to
page 29, Install Load
Balancing
shown immediately after these ‘standard’ installation instructions.
When Load Balancing has been installed, return to this point.
22. Route the incoming cables through the chosen enclosure entry point, ready to
connect to the appropriate terminals within the enclosure.
90°