23. Make sure the entry point into the enclosure can be sealed with an appropriate
cable gland.
24. Terminate the supply cable in the appropriate manner and connect it to the
connection point within the chargepoint.
25. If required, connect the Ethernet cable to the Smart Communications Module.
26. Make sure ALL debris is removed from the enclosure and that no debris is present
on any of the components.
NOTE:
Debris and similar pollutants can adversely affect the performance and working
life expectancy of components and will invalidate the product/component warranty.
IMPORTANT:
It is the responsibility of the installing engineer to satisfy themselves, that all cable
terminations throughout this product are secure and tight and have not become loose,
strained, or disconnected during transit and/or installation.
27. Reconnect any cables that may have been disconnected from the components
on the front panel.
28. Make sure all cable connections are secure and have not become loose or
damaged in transit or during installation.
29. Temporarily close the chargepoint enclosure for safety and security. Access to the
components will be needed during the configuration process.
30. If required, install the tethered cable plug holster(s) as described on
page 31
.
31. Switch ON the power to the chargepoint and perform electrical tests in
accordance with the current legislation applicable in the geographical region of
the installation.
32. Make sure you are satisfied that the electrical installation is complete.
Install Load Balancing
NOTE
: This manual assumes the installation of a single chargepoint. Whilst multiple
chargepoints can be connected in a similar way, installers may wish to consider
connecting/monitoring via third-party equipment.
If connecting/monitoring via third-party equipment, make sure you are fully aware of
the manufacturer’s instructions so that the device/system can be installed correctly and
in conjunction with the chargepoint installation.
If load balancing will be enabled on this chargepoint it should, ideally, be installed
alongside the ‘standard installation’.
If installing at a later date, work may be required to enable entry of the CT cable into the
chargepoint enclosure.