12. INSTRUCTIONS FOR COMMISSIONING PROTOCOL

FOR PELLET AND COMBI STOVES

The commissioning protocol is to be treated as a documents and 
serves as the basis for the warranty and guarantee terms� It is to 
be completed entirely, in particular the stove data and addresses, 
the work to be performed is to be ticked off after completion� The 
signatories confirm with their signatures that all the items on the list 
have been concluded properly�

Note

Please return 1 completed protocol for putting into service to 

 

RIKA Innovative Ofentechnik GmbH, Müllerviertel 20, 4563 
Micheldorf, Austria�

Electrical periphery

It is important that the connection socket in the electrical periphery 
is earthed� The operability of any room thermostat present must 
be checked� The execution of commands is to be established by 
phoning in the case of a GSM modem�

Exhaust gas system

The exhaust line, stove and combustion air inlet are part of the 
combustion system as a whole; therefore the correct execution 
must also be checked� The plug connections should be tight in 
general since the system works with excess pressure� The exhaust 
tube has a diameter of 100 mm for pellet stove, and of 130 mm / 
150 mm for the combi stove, which is sufficient for short distances� 
In the case of several changes in direction, the resistance of the 
exhaust system can increase with the flue to such an extent that 
the combustion quality suffers and/or noise arises from the greater 
flow speed� Correct determination of the chimney draught can only 
be performed at nominal thermal output and serves to evaluate the 
chimney� If the draught is more than 15 Pa, then a draught limiter 
should be installed�

Stove functions

These are the basic stove functions that are to be checked and 
ticked off� The stove is ready for operation if these functions are 
ensured�

Operator instruction

This is one of the most important points in the putting into operation� 
It is very important that the operator understands the stove properly 
and is prepared to assume responsibility for the basic tasks required 
for operational safety�

In particular the connection between special features of a biomass 
heating system and his obligations as well as the warranty and 
guarantee terms must be explained� e�g� non-tested pellets and screw 
blockers, lack of cleaning or maintenance and stove malfunctions� 
Thorough instruction can prevent many complaints�

Stove functions

Explanation of the processes in the stove during ignition, normal 
operation, cleaning phase etc�

Control

Explain operator’s possibilities to intervene, empty pellet container, 
room thermostat, GSM modem, functions and settings, program 
times if necessary� Operating instructions: Handover and reference 
to the content to the following points, is a document�

Warranty terms

Difference between warranty (statutory) and guarantee (voluntary), 
terms of guarantee, determination of wearing parts, reference to 
pellet quality to be used and the consequences of poor quality�

Cleaning instructions

Ash and dust occurs with a biomass heating unit� The fire trough is 
to be cleaned regularly with regular heating operation (in the case 
of pellet operation, the drilled air holes in particular must be free 
of residues)� The ash drawer is to be emptied regularly� The flue 
gas pipes are to be cleaned once or twice in the heating season 
depending on stove type; by a specialist company is best�

Maintenance

Note

We recommend at least once a year to have all maintenance 
carried out by your RIKA dealer�

Combustion

All doors must close tightly to prevent intake of false air�

Summary of Contents for Revivo 125

Page 1: ...Operating manual REVIVO 140 REVIVO 125...

Page 2: ...ording to ENplus A1 15 Pellet container refilling during operation 15 Pellet storage 15 6 TECHNOLOGY AND SAFETY FUNCTIONS 16 Operating comfort 16 Top efficiency lowest emissions 16 Pressure monitoring...

Page 3: ...20 Cleaning the flue pipes 21 Combustion air intake 21 Cleaning the convection air openings 21 Cleaning the pellet container 21 Checking door seal 21 Bearings 21 11 PROBLEMS POSSIBLE SOLUTIONS 22 Prob...

Page 4: ...Model Identifier Equivalent models REVIVO 125 REVIVO 140 RIKA Innovative Ofentechnik GmbH Andreas Bloderer M llerviertel 20 4563 Micheldorf Austria Test report no Applied harmonised standards Other ap...

Page 5: ...021 In case of doubt as well as missing or incorrect translations the German version is the only valid one Subject to technical and visual changes as well as layout and printing errors 2021 RIKA Innov...

Page 6: ...0 10 19 20 17 30 23 25 24 24 26 27 16 28 29 1 6 21 22 2 2 5 3 4 4 44 44 51 50 32 32 33 52 34 34 37 38 36 49 53 53 41 42 43 41 42 43 41 42 43 36 44 35 35 45 46 31 48 47 39 40 39 40 3 TECHNICAL DATA Spa...

Page 7: ...7 6 EN 64 65 66 60 61 59 61 67 62 63 58 68 69 70 71 56 57 75 81 87 91 90 85 89 88 85 86 85 93 94 82 84 83 79 92 77 78 76 80 74 73 95 96 97...

Page 8: ...100 107 106 106 104 102 105 105 109 110 114 113 112 111 115 108 157 156 155 153 154 128 129 127 126 133 145 132 152 147 148 149 150 151 125 124 121 120 123 122 130 131 134 141 146 136 138 137 137 143...

Page 9: ...9 8 EN Spare part overview exploded diagram REVIVO 125 173 160 168 172 171 170 169 166 163 165 164 161 167 174 175...

Page 10: ...Detent plate 1 Z37054 Detent plate 48 N112393 Micro switch 49 N111950 Hexagonal screw M05x10 Nr Art Nr Description 50 N105179 Hexagonal nut M10 51 L03330 Washer 52 LB00701 Rail angle right 53 Z36778 B...

Page 11: ...nting bracket 139 N112402 Rocker switch 140 N111604 Fuse 2 5 A 141 L03409 Support for drag chain 142 N112394 Chain 143 N112102 Differential pressure switch 144 N103990 Allen screw M04 x08 145 N111581...

Page 12: ...ature C 148 Chimney draft requirement Pa 3 The capacity in kg may deviate due to different pellet bulk densities The owner of small firing systems or the person authorised for the small firing system...

Page 13: ...on the stove to dry Q Laundry racks etc must be placed at a sufficient distance to the stove ACUTE DANGER OF FIRE Q When your stove is burning the use of highly inflammable and explosive materials in...

Page 14: ...ustion chamber door is to be kept closed when the stove is not in operation Q Foulingofthechimneyi e depositsofhighlyinflammablematerials such as soot and tar and subsequently fire in the chimney may...

Page 15: ...conducting measurements with a lignotester internal control Your pellet stove is only approved for the burning of pellets of tested quality Please ask your pellet stove dealer for tested fuel and a l...

Page 16: ...acknowledging the error message at the internal unit Note Maintenance and cleaning work must be performed if overheating occurs If this error recurs operation without danger is no longer guaranteed n...

Page 17: ...on must be calculated and shown with EN13384 1 and EN13384 2 Use only insulated double stainless steel tubes flexible aluminum or steel tubes are not permitted An inspection door for regular inspectio...

Page 18: ...the heating times set at the stove can also be activated You can see whether the external demand is currently activated in the INFO main menu in submenu item Info inputs If your stove receives an ext...

Page 19: ...ing cloth or newspaper Cleaning of the burn pot daily Make sure that the air vents are not blocked with ash or clinker Remove the clinker using the supplied brush and vacuum the burn pot The burn pot...

Page 20: ...Resets menu Note Yourstovemustbeswitchedoffandcooledbeforeanymaintenance work is performed Only work on the unit when the mains plug has been disconnected Cleaning the flue gas channels Disconnect yo...

Page 21: ...ush off any soot and dust deposits in the fire and in the flue pipes and vacuum Note Accumulated fly ash in the flue gas channels may impair the performance of the stove and pose a safety risk Combust...

Page 22: ...G MAINTENANCE Problem 2 Stove smells strongly and smokes outside Cause s Q Burning in phase taking into service Q Stove has accumulated dust and or dirt Possible solutions Q Wait to end of burning in...

Page 23: ...ions These are the basic stove functions that are to be checked and ticked off The stove is ready for operation if these functions are ensured Operator instruction This is one of the most important po...

Page 24: ...eight Room ventilation Exhaust hood outdoor connection WC extraction Comments Central vacuum cleaning system YES NO YES NO YES NO YES NO Chimney draft full load Outside temperature Plaster openings YE...

Page 25: ...ified for that type of stove The installation is performed by a RIKA certified technician If these points are not complied with the guarantee claim is void Any costs incurred by the manufacturer as a...

Page 26: ...eramic pane using a suitable tool Remove the seals and separate them from the frame if present Transparent glass ceramic can generally be recycled but must be separated into decorated and non decorate...

Page 27: ...27 26 EN...

Page 28: ...only valid one Subject to technical and visual changes as well as layout and printing errors 2021 RIKA Innovative Ofentechnik GmbH Z37505_REVIVO_EN 7 12 2021 RIKA Innovative Ofentechnik GmbH M llervie...

Reviews: