Installation
5.4
Operating position
5.5
Preparing the boiler
5.5.1
Boring the boiler plate
Drill the combustion chamber locking plate as shown in Fig. 14.
The position of the threaded holes can be marked using the ther-
mal screen supplied with the burner.
5.5.2
Blast tube length
The length of the blast tube must be selected according to the in-
dications provided by the manufacturer of the boiler, and in any
case it must be greater than the thickness of the boiler door com-
plete with its fettling.
For boilers with front flue passes 1)(Fig. 15) or flame inversion
chamber, a protection in refractory material 5) must be inserted
between the boiler fettling 2) and the blast tube 4).
The refractory can have a conical shape (minimum 60°).
This protective fettling must not compromise the extraction of the
blast tube.
For boilers with a water-cooled front piece, a refractory lining 2)-
5)(Fig. 15) is not necessary, unless expressly requested by the
boiler manufacturer.
Tab. L
5.6
Securing the burner to the boiler
Fit the heat insulation supplied onto the blast tube
4)(Fig. 15).
Fit the entire burner onto the boiler hole prepared previously
(Fig. 14), and fasten with the screws supplied.
WARNING
The burner is designed to operate only in
positions
1
,
2
,
3
and
4
(Fig. 13).
Installation
1
is preferable, as it is the only
one that allows the maintenance operations
as described in this manual.
Installations
2
,
3
and
4
permit operation but
make maintenance and inspection of the
combustion head more difficult.
DANGER
Any other position could compromise the cor-
rect operation of the appliance.
Installation
5
is prohibited for safety reasons.
Fig. 13
2
3
4
5
1
D7739
mm
A
DF
RLS 310
335
452
M18
RLS 410
335
452
M18
RLS 510
335
452
M18
RLS 610
350
452
M18
Fig. 14
20150238
Prepare a suitable lifting system using the rings
3)(Fig. 15), after removing the fixing screws 7) of
the casing 8).
WARNING
The seal between burner and boiler must be
airtight.
Fig. 15
20086747
Summary of Contents for RLS 310/EV O2 MX
Page 2: ...Translation of the original instructions ...
Page 52: ...20182250 50 GB Appendix Electrical panel layout 0 0 0 0 0 0 0 0 ...
Page 55: ...53 20182250 GB Appendix Electrical panel layout 0 ...
Page 56: ...20182250 54 GB Appendix Electrical panel layout ...
Page 57: ...55 20182250 GB Appendix Electrical panel layout 0 0 1 2 0 0 0 1 0 ...
Page 58: ...20182250 56 GB Appendix Electrical panel layout 0 0 0 1 0 2 0 0 0 0 0 0 0 30 3 3 0 0 1 0 ...
Page 66: ......
Page 67: ......