− Pump the heat transfer fluid around the circuit with an 

external  filling  pump  until  all  air  bubbles  have  been 

eliminated. Close the manual bleed valve and any vent 

valves opened previously.

 

− Turn handle on valve (VR) counter clockwise

 

− Temporarily raise the pressure in the system to 4 bar.

 

− Start up the system for about 20 minutes.

 

− Repeat air bleeding operation until system is completely 

free of air bubbles.

 

− set the system pressure.

 

− Close taps (A) and (B).

 

9

The set pressure must ensure that the one measured at the 

solar collectors is positive with respect to the ambient one 

(avoid depression in the solar field) and must be set con-

sidering both the safety valve opening pressure (6) and the 

solar expansion reservoir pre-charge pressure. To set the 

system pressure correctly, refer to the design manual.

 

0

Do not fill the system in bright, sunny conditions or if the 

collectors are hot.

 

9

Use a manual bleed valve, which should be installed at the 

highest point in the system, to ensure that all air bubbles 

have been eliminated from the circuit.

19 

DEVICE CLEANING AND MAINTENANCE

 

9

Service the system at least once a year and carry out the 

inspections specified in the relevant manual.

The following operations must be exclusively performed by 

Technical Assistance Service.

19.1 

Checking the seals

After  commissioning,  check  hydraulic  fitting  sealing.  Make 

sure there is no leakage close to electric components to avoid 

short-circuits.

19.2 

External cleaning

Clean the outside of the storage cylinder with a soft cloth 

damped in soapy water.

Use a dry rag to clean the insulation and the solar regulator dis-

play to remove any dust.

 

0

Do not use abrasive products, petrol or triethylene.

Summary of Contents for RBS 200 2S Ready-i

Page 1: ...cod 20122045 rev 1 03 2017 RBS 2S Ready i EN INSTALLATION OPERATION AND MAINTENANCE MANUAL...

Page 2: ...ISH CONTENTS The following symbols are used in this manual 9 9CAUTION Identifies actions that require caution and adequate preparation 0 0STOP Identifies actions that you MUST NOT do This manual Code...

Page 3: ...the product purchase documents to be presented to the R authorised Technical Assistance Service to request a service call under warranty 9 9Size the solar expansion tank so as to ensure complete ab s...

Page 4: ...te This lists the technical specifications and performance of the product Model bar W l W kW l 1 BOLLITORE SOLARE Modello Matricola Codice Anno m2 m2 kW m2 T067765IES SOLARBOILER Serial numb Code Year...

Page 5: ...6 bar 14 Tap A for system filling draining 15 Tap B for system filling draining 16 Delivery Valve solar plant delivery with built in non return valve 17 Outlet temperature gauge 18 Return Valve solar...

Page 6: ...3 1 51 W K Energy class B B B B PERFORMANCE RELATING TO INTEGRATION COIL Upper coil continuous efficiency ACS 10 45 C Vbu reference volume Coil delivery temperature 80 C T 20 C 16 1 23 31 4 31 4 kW 40...

Page 7: ...tank lower part 70 C 374 438 659 863 l 60 C 284 375 531 675 l 50 C 205 310 390 485 l DESCRIPTION SOLAR STATION TECHNICAL DATA Safety valve calibration pressure 6 bar Maximum operating temperature 110...

Page 8: ...than IP X0D 0 3 m 0 6 m 0 3 m 0 6 m 0 7 m NOTE the above indicated dimensions are recommended for a correct maintenance and access to the device 9 9When installing the boiler allow sufficient space ar...

Page 9: ...1 33 450 1 33 450 1 33 520 1 33 520 mm DF Flange internal diameter 130 130 130 130 mm A 1338 1838 1644 1988 mm B 1170 1670 1440 1784 mm C 1098 1438 1289 1653 mm D 953 1233 1064 1428 mm F 598 693 684 7...

Page 10: ...revailing standards of the installation country respect the polarity of the L1 Phase N Neutral con nections use cables with insulation and cross section conforming to applicable standards minimum cros...

Page 11: ...to terminal board M1 of solar regulator terminals L N GND making refer ence to the instructions provided in the specific regulator manual Once electrical connections are completed fasten cables using...

Page 12: ...r collectors For further information please refer to the glycol safety data sheet When using glycol not pre mixed Do NOT part fill the circuit with pure glycol then add water later Ensure that filling...

Page 13: ...ressure To set the system pressure correctly refer to the design manual 0 0Do not fill the system in bright sunny conditions or if the collectors are hot 9 9Use a manual bleed valve which should be in...

Page 14: ...20 3 Safety valve removal 9 9Remove when system has cooled down Before removing the safety valve Cut power off to the solar station and to the connected integration system by setting the system s mai...

Page 15: ...with the product 23 TEMPORARY SHUTDOWN To reduce to the environmental impact and save energy in case of brief absences week ends short trips etc and with exter nal temperatures above 0 C set the heat...

Page 16: ...lo 7 37045 Legnago VR www riello com The manufacturer strives to continuously improve all products Appearance dimensions technical specifications standard equipment and accessories are therefore liabl...

Reviews: