5
Installation Procedure
Page 9
Resonance Technology, Inc.
CinemaVision System Installation / Operation Manual: RTC-CV Rev 19
5.
Installation Procedure
The installation procedure consists of four major phases:
•
Installing the MR Laser Link Cable and Transducer Power Supply Cables
•
Magnet Room Component Interconnection
•
Equipment Room Component Interconnection
•
Control Room Component Interconnection
Before you begin the installation, determine the location where the transducer will be installed. It should be a
secure area next to the magnet and away from traffic. Please refer to the photo below for typical placement:
Video Goggles
Audio
Headset
Patient
Bed
Transducer
Unit