2 Final checks before commissioning
The first start-up is to be performed by your installation
engineer.
Make the gas line setting before commissioning.
Check the following points before starting the heater:
Hydraulic circuit:
`
Check that the installation and boiler are adequately filled with
water and correctly irrigated and bled.
`
Check that the hydraulic connections are leak tight.
Gas circuit:
`
Check the adjustment of the gas line:
- Connect a manometer to the pressure socket located on the
manifold.
- Check that the nozzle pressure and the start-up pressure match
the pressures given in the relevant chapter: Pressure settings and
calibrated injector markings.
If necessary, adjust the pressure as shown in the relevant
chapters: Setting the injector pressure.
Electrical connectors:
Check that the connectors under the control panel are correctly fitted:
1
Ignition circuit
2
Gas pressostat
3
Gas valve circuit
4
Leak proofing system (Options RE 30)
Summary of Contents for GAS 460 S
Page 1: ...Remeha Gas 460 S Gas fired boilers Technical instructions English 06 02 06...
Page 23: ...23 06 02 06 300005247 001 B Remeha Gas 460 S Base frame Draught diverter...
Page 24: ...24 Remeha Gas 460 S 06 02 06 300005247 001 B Insulation...
Page 25: ...25 06 02 06 300005247 001 B Remeha Gas 460 S Control panel K Control panel K Components...
Page 26: ...26 Remeha Gas 460 S 06 02 06 300005247 001 B Metal casing for control panel K...
Page 27: ...27 06 02 06 300005247 001 B Remeha Gas 460 S Gas line 20 mbar Circuit separation transformer...
Page 28: ...28 Remeha Gas 460 S 06 02 06 300005247 001 B Cladding...
Page 34: ...34 Remeha Gas 460 S 06 02 06 300005247 001 B...