13
06/02/06 - 300005247-001-B
Remeha Gas 460 S
4 Setting the injector pressure
Setting the pressure 2nd stage
The pressure must be set by a qualified professional.
The boiler must be commissioned after having checked the points
covered in this chapter: Final checks before commissioning.
- Connect a manometer to the pressure outlet.
- Run the boiler at 2nd stage, activating the thermostat(s).
- Set the pressure at the injectors as follows:
- Free the cylindrical split head screw
C
by around one turn. Fully
unscrew the setting button
D
(anti-clockwise). Tighten the screw
C
.
- Set the pressure at the injectors by turning the screw on the
regulator
B
. By turning to the right, you increase and, by turning to
the left, you decrease the principal flow.
If you find you cannot tighten screw
B
any further before
reaching the desired pressure, unscrew
B
again by a quarter
turn and continue the setting by turning
D
after freeing the
inhibitor screw
C
.
- On propane, the regulator
B
is fully tightened. It is not used.
Summary of Contents for GAS 460 S
Page 1: ...Remeha Gas 460 S Gas fired boilers Technical instructions English 06 02 06...
Page 23: ...23 06 02 06 300005247 001 B Remeha Gas 460 S Base frame Draught diverter...
Page 24: ...24 Remeha Gas 460 S 06 02 06 300005247 001 B Insulation...
Page 25: ...25 06 02 06 300005247 001 B Remeha Gas 460 S Control panel K Control panel K Components...
Page 26: ...26 Remeha Gas 460 S 06 02 06 300005247 001 B Metal casing for control panel K...
Page 27: ...27 06 02 06 300005247 001 B Remeha Gas 460 S Gas line 20 mbar Circuit separation transformer...
Page 28: ...28 Remeha Gas 460 S 06 02 06 300005247 001 B Cladding...
Page 34: ...34 Remeha Gas 460 S 06 02 06 300005247 001 B...