17
Raychem-IM-H58033-XLTracePipeFreezeProtectionCOM-EN 18/01
2
Installation guidelines
Heating cable
Heating cable
beneath
insulation
and pipe hanger
Heating cable
over pipe hanger
Pipe hanger
under insulation
Pipe hanger
over insulation
Insulation over
pipe hanger
Heating cable
Figure 16: Pipe hanger
2.4
heating Cable Connections
general requirements
All XL-Trace systems require a power connection
and end seal kit. Splice and tee kits are used as
required. Use Table 3 (for aboveground applications)
and Table 4 (for belowground applications) to select
the appropriate connection kits.
When practical, mount connection kits on top of the
pipe. Electrical conduit leading to power connection
kits must have low-point drains installed to avoid
condensation entry into the heating system. All heat-
ing cable connections must be mounted above grade
level.
If your design has an exposure temperature >150°F
(65°C) but < 185°F (85°C), install all connections kits
off the pipe.
WarnIng: Connection kit approvals and perfor-
mance are based on the use of specified parts only.
Do not use substitute parts or vinyl electrical tape.
Follow installation instructions provided with each
kit.