31
www.ratio-electric.com
11
. Gently pull the excess ethernet cable out of the charger.
12
. Repeat the installation steps for Sub chargers in daisy chain configuration.
Note:
Only the Main Controller is directly connected to the sensorbox.
5 . 8 .
Checks before finishing the installation
•
Check if all phase, neutral and earthing wires are properly connected.
•
Check if the data cables are wired correctly and the order of the coloured wires matches
on both sides.
•
Check if all cables are free of damage and are properly secured.
•
Check if the current transformers are properly installed around the phase wires of the
main power grid.
•
Check if the current transformers are plugged into the correct phase inputs of the
sensorbox.
•
Check if the housing is correctly closed and no loose wires are visible or exposed.