FORM QWC3-NM1
ISSUE DATE: 11/20/2020
SECTION 4 – INSTALLATION
QUANTECH
38
The length of cable to these terminals
must not exceed 24 ft. (7.5 m).
Flow Switch (SF)
A chilled liquid flow switch of suitable type must be
connected to terminals 13 and 14 to provide adequate
protection against loss of liquid flow.
After connection, do not switch on mains
power to the unit until it has been com-
missioned by Quantech Authorized per-
sonnel. Some internal components are
live when mains is switched ON.
The unit ON/OFF rocker switch on the front of the
control panel has been set in the OFF position at the
factory.
This switch MUST remain in the OFF position until
the unit is commissioned by Quantech Authorized per-
sonnel. If the switch is set to the ON position before
commissioning then it must be reported to Quantech,
otherwise the warranty may be invalidated.
Remote Start/stop
Remote Start and Stop is accomplished by a contact
placed between Terminals 13 and 51 on the CTB1 ter-
minal strip. If this function is not utilized, the termi-
nals must be jumpered for the chiller to run.
POWER WIRING
All electrical wiring should be carried out in accor-
dance with local regulations. Route properly sized ca-
bles to cable entries on the bottom of the control panel.
For wiring specifications, see SECTION 5 – TECHNI-
In accordance with National Electric Code (N.E.C.),
it is the responsibility of the user to install overcurrent
protection devices between the supply conductors and
the power supply terminals on the unit.
To ensure that no eddy currents are set up in the metal
gland plate the cables forming each 3-phase power
supply must enter via the same hole in the gland plate.
If separate entries for each cable forming the 3-phase
supplies are used, the metal gland plate must be re-
placed by a non-metallic gland plate, with due regard
given to sealing the panel to NEMA 1.
All sources o f supply to the unit must be
taken via a common point of isolation (not
supplied by Quantech).
Units with Single-Point Power Supply Wiring
Models require one field provided 200 VAC, 3-phase,
60 Hz; 230VAC, 3-phase, 60 Hz; 380 VAC, 3-phase,
60 Hz; 460 VAC, 3-phase, 60 Hz; 575 VAC, 3-phase,
60 Hz, ground supply to the unit with circuit protec-
tion.
Connect the 3-phase supply to the terminal block or
Non-fused Disconnect Switch located in the common
input section using the wire sizes detailed in
Connect the earth wire ground to the main protective
earth terminal in the common input section.
Units with Multi Point Power Supply Wiring
Units require two field provided 200 VAC, 3-phase, 60
Hz; 230VAC, 3-phase, 60 Hz; 380 VAC, 3-phase, 60
Hz; 460 VAC, 3-phase, 60 Hz; 575 VAC, 3-phase, 60
Hz, supplies with circuit protection and a separate con-
trol supply with circuit protection (200 VAC, 3-phase,
60 Hz; 230VAC, 3-phase, 60 Hz; 380 VAC, 3-phase,
60 Hz; 460 VAC, 3-phase, 60 Hz; 575 VAC, 3-phase,
60 Hz, +ground).
Connect each of the 3-phase supplies to the door inter-
locked circuit breakers located in the power sections,
using the wire sizes detailed in Section 5.
Connect each of the earth grounds to the main protec-
tive earth ground terminals in the power sections.
Connect the control supply to the door interlocked
emergency stop device located in the common input
section, using the wire sizes detailed in Section 5.
Connect the earth ground to the main protective earth
terminal in the common input section.
Summary of Contents for QWC3050T-200T
Page 4: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 4 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 10: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 10 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 28: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 28 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 144: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 144 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 152: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 152 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 166: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 166 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 185: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 185 NOTES...