FORM QWC3-NM1
ISSUE DATE: 11/20/2020
SECTION 6 – COMMISSIONING
QUANTECH
108
JOHNSON CONTROLS
1
8. Visually inspect wiring (power and control). Wiring
MUST meet N.E.C. and local codes. .......................
9. Check tightness of power wiring inside the power
panel on both sides of the motor contactors and
overloads. ...............................................................
10. Check for proper size fuses in main and control cir-
cuits, and verify overload setting corresponds with
RLA and FLA values in electrical tables. ..................
11. Assure 120VAC Control Power to TB1 has 15 amp
minimum capacity. ...................................................
12. Be certain all water temp sensors are inserted com-
pletely in their respective wells and are coated with
heat conductive compound. ....................................
13. Assure that evaporator TXV bulbs are strapped
onto the suction lines at 4 or 8 o'clock positions or
suction temps. sensors if EEVs are installed. .........
B. COMPRESSOR HEATERS
(POWER ON - 24 HOURS PRIOR TO START)
Apply 120VAC and verify its value between terminals 5 and
2 of CTB2. The voltage should be /- 10%. ....
Power must be applied 24 hours prior to start-up
Each heater should draw approximately 0.5-1A.
A. CHECKING THE SYSTEM PRIOR TO INITIAL
START (NO POWER)
Unit Checks
1. Inspect the unit for shipping or installation damage
2. Assure that all piping has been completed .............
3. Visually check for refrigerant piping leaks ...............
4. Open suction line ball valve, discharge line ball
valve, and liquid line valve for each system. ...........
5. The compressor oil level should be main-
tained so that an oil level is visible or splash-
ing in sight glass when fully loaded. At shut-
down, the oil level should be between the
bottom and middle of the oil equalizing sight glass.
6. Assure water pumps are "ON". Check and adjust
water pump flow rate and pressure drop across
the cooler (see "Operational Limitations" in IOM).
Verify flow switch operation. ....................................
damage to the heat exchanger (evapora-
tor).
7. Check the control panel to ensure it is free of for-
eign material (wires, metal chips, etc.). ....................
STARTUP CHECKLIST
QWC
3050T - 200T STYLE A, 60 HZ,
STARTUP CHECKLIST
NEW RELEASE
Form QWC3-CL1 (317)
STARTUP CHECKLIST
The following work must be completed in accordance with installation instructions:
CUSTOMER: ____________________________________
ADDRESS: _____________________________________
PHONE: ________________________________________
JCI TEL NO: _____________________
JCI ORDER NO: __________________ JCI CONTRACT NO: ______________
JOB NAME: ____________________________________
LOCATION: ____________________________________
CUSTOMER ORDER NO: _________________________
CHILLER MODEL NO
: ____________________________
The work (as checked below) is in process and will be completed by: _____________ / ____________ /
___________
UNIT SERIAL NO
: _______________________________
Month
Day
Year
Summary of Contents for QWC3050T-200T
Page 4: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 4 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 10: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 10 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 28: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 28 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 144: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 144 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 152: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 152 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 166: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 166 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 185: ...FORM QWC3 NM1 ISSUE DATE 11 20 2020 QUANTECH 185 NOTES...