Health and fresh!
10
9. INSPECTION ITEMS AFTER INSTALLATION
Items to be checked
Situation caused by improperly i Items
to be checked installation
Is installation stable?
The equipment may fall off or shake.
Is heat insulation adequate?
Damage objects close to equipment.
Does power voltage same as voltage
shown on product nameplate?
Equipment failure.
Does wire connection correct?
Equipment failure.
Does electricity ground connected safely? There is electricity leakage risk.
10. ATTENTION
Due to thermal expansion and contraction, the heater would make noise when turning
on or off. It’s a normal phenomenon, and won’t make bad affection.
11. INSPECTION ITEMS FOR COMMISSIONING
1. Do not connect power until installation is complete.
2. All wires connection are correct and firm.
3. All scattered objects must be removed from radiant heater body.
4. Connect power and check heater is operating correctly.