R
September 24, 2015
7014-188L
Page 41
1200-I Pellet Insert
G. Baffl e Removal
a.
Be sure the appliance is allowed to cool, has been
unplugged and the exhaust blower is off.
b. Open glass door.
c. Grasp the bottom of the baffl es and pull up to dis-
lodge from hook attachment.
d. Use a standard screw driver to unlatch the covers
beneath the baffl es of each side.
e. Re-install in reverse order.
F. Igniter Replacement
a. Be sure the appliance is allowed to cool, has been
unplugged and the exhaust blower is off. Remove the
ash pan.
b. The wire leads to the igniter are connected to the wire
harness with 1/4 inch male / female spade connectors.
These wires will pull forward approximately 4 to 5
inches (102mm to 127mm). Disconnect the spade
connections and remove the igniter from the chamber.
Loosen the thumb screw and slide igniter out.
c. Install new igniter into the chamber and tighten the
thumb screw. Re-connect the wires to the 2 leads with
the spade connectors.
d. Push excess wire leads to take-up the 4 to 5 inches
(102mm to 107mm) previously pulled out. This will
keep the wires out of the way of the ash pan. Double
check that the igniter wires are clear of any movement,
i.e. ash pan, fi repot cleaning rod, etc.
f. Re-install the ash pan and re-connect the power.
Figure 41.1
Igniter
Igniter Bracket
Thumb Screw
Summary of Contents for PELLET INSERT CB1200MI-MBK
Page 52: ...Page 52 7014 188L September 24 2015 R 1200 I Pellet Insert F Warranty Policy ...
Page 53: ...R September 24 2015 7014 188L Page 53 1200 I Pellet Insert ...
Page 54: ...Page 54 7014 188L September 24 2015 R 1200 I Pellet Insert ...
Page 55: ...R September 24 2015 7014 188L Page 55 1200 I Pellet Insert ...