background image

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO BLK ML-G10/t

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO BLK ML-G10/t

20

21

5 Grounding

Protective Grounding

In order to prevent electrical shock or fire, the frame of the mod-
ule as well as any non-current-carrying metal parts of the system 
must be grounded. While this section provides some informa-
tion about grounding the Qcells frames and modules, reference 
should be made to local statutes and regulations for specific 
requirements on grounding. The U.S. National Electrical Code ad-
dresses these issues in Article 250. A module with exposed con-
ductive parts is considered to be in compliance with this standard 
only when it is either electrically grounded in accordance with the 
manufacturer’s instructions and the requirements of the National 
Electrical Code, ANSI/NFPA 70 (2014-2017), or when the bonding 
means has been evaluated with this module to UL 2703.

Proper grounding is achieved by bonding all exposed non-cur-
rentcarrying metal equipment to the appropriately sized equip-
ment grounding conductor (EGC) or racking system that can be 
used for integrated grounding.

Qcells frames are protected from corrosion with an anodized 
coating, which has to be penetrated in order to ensure proper 
bonding. The different methods listed below are suggested 
methods for an appropriate bond between the frame and the 
EGC or racking system (that will have to be properly grounded). 
The method appropriate for any individual installation will depend 
on multiple factors.

 

Dimensions shown are in inches.

0.177” (+0.008/-0)

±0.08

0.79”

0.47”

±

0.08

Option A: Use of a grounding lug

A listed grounding lug can be bonded to the frame using the 
grounding holes pre-drilled in the frame. These holes are marked 
with a ground symbol, as shown below on the frame section 
drawing: To install the grounding lug, follow the specified instruc-
tions of the manufacturer. The grounding lug should be made of 
stainless steel or tin plated metals such as aluminum to avoid cor-
rosion.

The grounding lug should be attached to the frame grounding 
hole using a stainless steel screw, toothed lock washer or KEPS 
nut (in order to penetrate the anodized layer) and backing nut. 
Care should be taken to avoid the use of grounding hardware of 
dissimilar metals, which may lead to corrosion.

Option B: Integrated grounding methods

The Qcells modules can be bonded with the racking system us-
ing UL1703 or UL2703 certified integrated grounding methods. 
The racking system will then have to be grounded so that the 
overall system is properly grounded. The listed racking system 
and grounding device should be installed in accordance with 
the manufacturers’ instructions. An example of such integrated 
grounding method is the use of a WEEB clip or Schletter plate 
between the module and the racking system, when mounting the 
module.

The WEEB washers are generally compatible with Qcells mod-
ules, however each combination module / racking system requires 
a specific WEEB washer size. Note that WEEB clips are intended 
for single use only; they must not be reused after removal or 
loosening. Refer to Wiley’s installation instructions for the specific 
use of WEEB washers.

An example of such integrated grounding method is the use of a 
washer recognized as meeting UL2703 requirements between 
the module and the racking system, when mounting the module. 
For example, WEEB washers are generally compatible with Qcells 
modules, however each combination module / racking system 
requires a specific WEEB washer size. Note that WEEB washers 
are intended for single use only; they must not be reused after 
removal or loosening. Refer to Wiley’s installation instructions for 
the specific use of WEEB washers.

PV Laminate

Backing Nut (Stainless Steel)

Toothed Lock Washer (Stainless 
Steel)

Grounding Lug (Stainless Steel 
or tin-plated metal)

Equipment 
Grounding 
Conductor

Aluminum 
Frame

Screw (Stainless Steel)

6 Faults and defects

Danger! 
Risk of fatal injury due to electric shock!

  Do not attempt to fix any problems yourself (e.g., glass cracks, 

damaged cables).

  Please contact an installer or Qcells Technical Customer Ser-

vice Department.

7 Disposal

  Do not disconnect modules by yourself.
 Please commission a trade specialist.
  Dispose of modules in accordance with the local disposal reg-

ulations.

Summary of Contents for Q.PEAK DUO BLK ML-G10/t Series

Page 1: ...Installation and operation manual Q PEAK DUO BLK ML G10 t solar module series ...

Page 2: ...ator are responsible for com pliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times during the installation operation and maintenance of the solar modules Installation and Operation Manual Other applicable documents such as country specific reg ulations for pressure equipment operational safety hazard ous goods and env...

Page 3: ...OR INCORRECT USE OF SOLAR MODULES VOIDS THE LIMITED WARRANTY AND MAY CREATE A SAFETY HAZARD AND RISK PROPERTY DAMAGE THIS INCLUDES IMPROPER IN STALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION Attention This marking indicates that this product should not be disposed of with other household waste within the EU Recycle this product properly to prevent poss...

Page 4: ...Ensure that no additional forces are applied through the mount ing system into the module except for the wind and snow loads Additional forces and moments of torque at the mounting po sitions caused by torsions displacements or vibrations in the mounting system are not allowed Ensure that the clamps and the mounting frame are compatible Clamp System Recommendations Use customary clamps that satisf...

Page 5: ...m long side 11 8 17 7 300 450mm CL6c outer clamps 0 79 19 7 20 500mm middle clamps 25 2 48 8 640 1240mm 3600 3000 2400 2000 outer clamps 0 79 13 8 20 350mm middle clamps 25 2 48 8 640 1240mm 4000 4000 2660 2660 CL6d short side 0 79 9 84 20 250mm long side 25 2 48 8 640 1240mm 4000 3600 2660 2400 The below mounting options are only possible under certain conditions MOUNTING OPTION POSITION OF CLAMP...

Page 6: ... load 2 Planning 2 3 Mounting options 2 Planning 2 4 Electrical layout Module Selection For detailed key electrical data please refer to the actual data sheet referring to the relevant Module available at www qcells com For maximum energy yields mismatches of specified electric current IMPP of more than 5 should be avoided for all mod ules connected in series Safety Factor During normal operation ...

Page 7: ...ock Do not install damaged modules Inform your distributor of any damages immediately Warning Fire Risk Do not install modules indoors Do not install modules on moving objects 3 Installation 3 1 Safety and Transport Note Module damage may occur Do not stack modules Note Module damage may occur Do not install modules near flammable gas vapors Do not install modules in close proximity to air condi t...

Page 8: ... of fatal injury due to electric shock Only use dry insulated tools Do not carry out the installation alone Only install undamaged modules and components Do not modify the module e g do not drill any additional holes 3 Installation 3 3 Module installation Option 1 Fasten the module with 4 clamps in the specified clamping range see Fig 2 p 7 Tighten clamps according to manufacturer s instruc tions ...

Page 9: ...paration Be sure to observe the time intervals specified by the inverter manufacturer after switching off the inverter Make sure that the plugs can not be connected unintentionally Before working on the contacts check them for safety ex tra low voltage Danger Risk of fatal injury due to electric shock Only use dry insulated tools for electrical work Danger Risk of fatal injury due to electric shoc...

Page 10: ...her audibly Danger Risk of fatal injury due to electric shock Ensure that all electrical components are in a proper dry and safe condition To avoid complex cabling arrangements it is often advantageous to rotate some modules 180 Module orientation can clearly be identified from the front side by the serial number and barcode labelled behind the module glass on the side with negative connection cab...

Page 11: ...should be attached to the frame grounding hole using a stainless steel screw toothed lock washer or KEPS nut in order to penetrate the anodized layer and backing nut Care should be taken to avoid the use of grounding hardware of dissimilar metals which may lead to corrosion Option B Integrated grounding methods The Qcells modules can be bonded with the racking system us ing UL1703 or UL2703 certif...

Page 12: ...age may occur Remove snow and ice carefully without force e g with a very soft broom Do not scratch off dirt Module cleaning has to be done by qualified personnel ac cording to the state of the art and taking into account all rele vant safety issues and general product properties e g but not restricted to electrical safety mechanical stability load limits depending on the actual mounting options c...

Page 13: ...nstallation manual solar modules Q PEAK_DUO_BLK_ML G10 X t_modules_series_2023 02_Rev02_NA HANWHA Q CELLS AMERICA INC 400 Spectrum Center Drive Suite 1400 Irvine CA 92618 USA EMAIL WEB TEL hqc inquiry qcells com www qcells com 1 949 748 59 69 ...

Reviews: