Option 1:

 

Ä

Fasten the module with 4 clamps in the 
specified clamping range, 
see Fig. 2, p. 7.

 

Ä

Tighten clamps according to 
manufacturer’s instructions.

 

Ä

Maintain an interval of at least 10 mm between 
two modules along the short side and 5 mm 
along the long side.

10 mm

5 mm

EU

Note! Module damage may occur!

 

Ä

Do not subject modules to mechanical tension. 
Max. torsion 10 mm/m.

Option 2:

 

Ä

Install the module at the 4 mounting points, 
see Fig. 2, p. 7.

 

Ä

Tighten screws according to 
manufacturer’s instructions.

3  INSTALLATION

3.3 MODULE INSTALLATION

Option 3:

 

Ä

Install the module using mounting profiles, 
see Fig. 2, p. 7.

DANGER! 
Risk of fatal injury due to electric shock!

When disconnecting an electric circuit carrying direct current, 
electric arcs can occur that may result in life-threatening injuries.

 

Ä

Do NOT unplug the cable when under load.

 

Ä

Do NOT connect any exposed cable ends.

 

Ä

Electrical work may only be performed by qualified and 
skilled personnel (see page 3).

A solar module generates electrical current and voltage even 
at a low intensity of illumination. Sparks and electric arcs may 
result from the separation of a closed circuit. These can result 
in life-threatening injuries. The danger increases when several 
modules are connected in series.

 

Ä

Please be aware of that the entire open circuit voltage is 
active even at low levels of solar irradiation.

 

Ä

Please follow the valid national regulations and safety guidelines 
for the installation of electrical devices and systems.

 

Ä

Please make sure to take all necessary safety precautions. 
With module or phase voltages of more than 120 V, the safety 
extra-low voltage range is exceeded.

 

Ä

Carry out work on the inverter and the wiring with extreme 
caution.

 

Ä

Ensure that the modules are disconnected at the inverter 
prior to separation.

 

Ä

Be sure to observe the time intervals specified by the inverter 
manufacturer after switching off the inverter.

 

Ä

Make sure that the plugs can not be connected unintentionally.

 

Ä

Before working on the contacts, check them for safety extra-low 
voltage.

Danger! Risk of fatal injury due to electric 
shock!

 

Ä

Never open the junction box.

 

Ä

Do not remove bypass diodes.

Danger! Risk of fatal injury due to electric 
shock!

 

Ä

Never touch live contacts with bare hands.

 

Ä

Cover connectors by suitable protective caps 
until installation.

Danger! Risk of fatal injury due to electric 
shock!

 

Ä

Insulate any exposed cable ends.

 

Ä

Only connect cables with plugs.

Danger! Risk of fatal injury due to electric 
shock!

 

Ä

Only use dry, insulated tools for electrical 
work.

4  ELECTRICAL CONNECTION

4.1  SAFETY

Summary of Contents for Q.PEAK DUO XL-G10.2

Page 1: ...INSTALLATION AND OPERATION MANUAL Q PEAK DUO XL G10 2 and Q PEAK DUO XL G10 c solar module series Valid for Africa Europe LatinAmerica South America...

Page 2: ...uch as country specific regulations for pressure equipment operational safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable laws and r...

Page 3: ...egardingregulationsandpermitrequirements prior to installation of the solar power system Other applicable documents In addition to this Manual following technical information are relevant DOCUMENT TYP...

Page 4: ...l requirements Compliant with local snow and wind loads Properly fastened to the ground the roof or the fa ade Forces acting on the module are relayed to the mounting substructure Ensures sufficient r...

Page 5: ...0 3600 3000 2400 2000 IP1 TB1b 713 TB2b Outer side 713 Inner side 713 454 CL1b 300 550 3000 2400 2000 1600 TB1a 908 2500 2400 1660 1600 TB2a Outer side 908 Inner side 908 713 454 2700 2400 1800 1600 C...

Page 6: ...en laminate and mounting rails CL1b CL2b CL3 mCL3 FB2 mFB2 A minimum support depth of 15mm is required on the back side of the module CL5 The minimum required support depth on the module backside is 1...

Page 7: ...dules in the string Parallel Connection Modules may be damaged by the occurrence of reverse currents caused by module defects ground leaks or defective insulation Ensure that the maximum reverse curre...

Page 8: ...shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any objects to fall onto modules 3 INSTALLATION 3 1 SAFETY AND TRANSPORT Danger R...

Page 9: ...s may result from the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Please be aware of that the entire...

Page 10: ...d skilled personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of the same type and manufacturer Use minimum 4mm2 co...

Page 11: ...TER INSTALLATION Ensure that the cabling is not exposed and or hanging and is protected from dirt moisture and mechanical friction Ensure that cables are protected from abrasion tension compression an...

Page 12: ...rface damage may occur Remove snow and ice carefully without force e g with a very soft broom Do not scratch off dirt Module cleaning has to be done by qualified personnel according to the state of th...

Page 13: ...ual solar modules Q PEAK DUO XL G10 2_G10 c_2022 01_Rev01_AU HANWHA Q CELLS AUSTRALIA PTY LTD Suite 1 Level 1 15 Blue Street North Sydney NSW 2060 Australia TEL 61 0 2 9016 3033 FAX 61 0 2 9016 3032 E...

Reviews: