INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO-G6.X+ – Q CELLS

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO-G6.X+ – Q CELLS

18

19

Protective Grounding

 

Ä

The modules must be grounded in accordance with the local 
statutory regulations.

Functional grounding

• 

For installations located in tropic regions (between 23.5° N 
and 23.5° S) with a module tilt of < 5°, functional grounding 
at the negative generator connection on the DC side must 
be implemented.

 

Ä

Ensure that the difference of potential between the negative 
generator connection and the local earth potential (e.g. 
substructure, PE of the inverter) on each string in operation 
mode is positive or 0 V.

 

Ä

Follow the directions of the inverter manufacturer and local 
statutory regulations.

 

Ä

Only use inverters which include lincensed grounding kits.

 

Ä

Functional grounding has also to be implemented in installation 
sites with increased salt content in the air. (e.g. close to the 
sea).

DANGER!  
Risk of fatal injury due to electric shock!

 

Ä

Do not attempt to fix any problems yourself (e.g. glass cracks, 
damaged cables).

 

Ä

Please contact an installer or Q CELLS Technical Customer 
Service Department.

 

Ä

Do not disconnect modules by yourself.

 

Ä

Please contact an installer or Q CELLS Technical Customer 
Service Department.

 

Ä

Dispose of modules in accordance with the local disposal 
regulations.

Q CELLS solar modules are known for a long operating life and 
minimal maintenance effort and expense. Dirt and grime are 
usually washed away by rain. If the module is fully or partially 
shaded by dirt or debris (e.g., plants, bird droppings), it needs 
to be cleaned to prevent a loss of performance.

Maintenance

 

Ä

The PV system has to be inspected regularly by certified 
personnel

 

Ä

The time intervals and extent of the inspection can depend 
on local circumstances (e.g. salt, ammonia content in the air, 
high humidity etc.). The customer/operator must inform himself 
about time intervals and extend of necessary inspections. 

 

Ä

Inspections have to be performed especially after extraordinary 
events (e.g. storm, hail, high snow loads etc.)

 

Ä

During the inspections it has to be checked that the compo-
nents are secure, undamaged and clean

Cleaning

WARNING!  
Risk of injury due to hot and live modules!

 

Ä

Only clean modules that have cooled down.

 

Ä

Do not carry or wear any electrically conductive parts.

WARNING!  
Risk of falling due to unsecured access! 

 

Ä

Never access the installation area alone or without taking 
adequate security precautions.

 

Ä

Please commission a trade specialist.

NOTE!  
Module surface damage may occur! 

 

Ä

Remove snow and ice carefully without force (e.g. with a 
very soft broom).

 

Ä

Do not scratch off dirt.

 

Ä

Rinse dirt (dust, leaves, etc.) off with lukewarm water or use an 
alcohol based glass cleaner. Do not use abrasive detergents 
or surfactants. 

 

Ä

Use a soft cellulose cloth (kitchen roll) or sponge to carefully 
wipe off stubborn dirt. Do not use micro fleece wool or 
cotton cloths.

Isopropyl alcohol (IPA) can be used selectively to remove 
stubborn dirt and stains within one hour after emergence.

 

Ä

Please follow the safety guidelines provided by the IPA 
manufacturer. 

 

Ä

Do not let IPA run down between the module and the frame 
or into the module edges.

Note! Module damage may occur!

 

Ä

Do not clean modules with water if there is a 
risk of frost.

5  GROUNDING

6  FAULTS AND DEFECTS

7  DISPOSAL

8  MAINTENANCE AND CLEANING

 

Ä

Free the substructure from any dirt and debris 
(leaves, bird nests, etc.).

 

Ä

Remove dirt with lukewarm water or alcohol 
based glass cleaner, a broom, or a soft cloth.

 

Ä

Do not use surfactants, rotating brushes, 
scrapers, or any high-pressure water cleaning 
equipment.

Summary of Contents for Q.PEAK DUO BLK-G6

Page 1: ...INSTALLATION AND OPERATION MANUAL Q PEAK DUO G6 X solar module series Valid for Africa Europe LatinAmerica South America ...

Page 2: ...ssure equipment operational safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable laws and requirements in particular inter national country specific regional laws and stipulations governing the planning installation and operation of solar power systems and work on roofs Any valid international national and regional regulations gover...

Page 3: ...ionsandpermitrequirements prior to installation of the solar power system Your financial success depends on the fulfillment of these requirements Other applicable documents In addition to this Manual following technical information are relevant DOCUMENT TYPE Product data sheet Packaging and transport information Fig 1 External dimensions and components for Q PEAK DUO G6 Q PEAK DUO G6 Q PEAK DUO BL...

Page 4: ...tructure Ensures sufficient rear ventilation of the module Avoid the usage of different metals to prevent contact corrosion Allows for stress free expansion and contraction due to temperature fluctuations Ä Ä Ensure that no additional forces are applied through the mounting system into the module except for the wind and snow loads Additional forces and moments of torque at the mounting positions c...

Page 5: ...ws and washers diameter 15 8mm or 0 62in for FB1 and FB2 mounting Module Selection Fordetailedkeyelectricaldata pleaserefertotheactualdatasheet referring to the relevant Module available at www q cells com Ä Ä For maximum energy yields mismatches of specified electric current IMPP ofmorethan5 shouldbeavoidedforallmodules connected in series Safety Factor During normal operation a module may genera...

Page 6: ...ot install damaged modules Ä Ä Inform your distributor of any damages immediately Note Module damage may occur Ä Ä Do not stack modules Note Module damage may occur Ä Ä Do not install modules near flammable gas vapors Ä Ä Do not install modules in close proximity to air conditioning systems Note Module damage may occur Ä Ä Do not drop modules Note Module damage may occur Ä Ä Only make modification...

Page 7: ...shock Ä Ä Only use dry insulated tools Ä Ä Do not carry out the installation alone Only install undamaged modules and components Ä Ä Do not modify the module e g do not drill any additional holes 3 INSTALLATION 3 2 PREPARATION OF INSTALLATION Option 1 Ä Ä Fasten the module with 4 clamps in the specified clamping range see Fig 2 p 7 Ä Ä Tighten clamps according to manufacturer s instructions Ä Ä Ma...

Page 8: ...ervals specified by the inverter manufacturer after switching off the inverter Ä Ä Make sure that the plugs can not be connected unintentionally Ä Ä Beforeworkingonthecontacts checkthemforsafetyextra low voltage Danger Risk of fatal injury due to electric shock Ä Ä Never open the junction box Ä Ä Do not remove bypass diodes Danger Risk of fatal injury due to electric shock Ä Ä Never touch live con...

Page 9: ...geous to rotate some modules 180 Ä Ä Module orientation can clearly be identified from the front side by the serial number and barcode labelled behind the module glass on the side with negative connection cable EN Inverter 180 180 SOLAR Ä Ä Ensure that all necessary safety and functional tests have been carried out according to applicable standards Note Module damage may occur Ä Ä Ensure that the ...

Page 10: ...tified personnel Ä Ä The time intervals and extent of the inspection can depend on local circumstances e g salt ammonia content in the air high humidity etc The customer operator must inform himself about time intervals and extend of necessary inspections Ä Ä Inspectionshavetobeperformedespeciallyafterextraordinary events e g storm hail high snow loads etc Ä Ä During the inspections it has to be c...

Page 11: ...lee 17 21 06766 Bitterfeld Wolfen Germany TEL 49 0 34946699 23222 FAX 49 0 34946699 23000 EMAIL sales q cells com WEB www q cells com Subject to change without notice Q CELLS Installation manual solar modules Q PEAK DUO G6 X _2019 06_Rev01_EN ...

Reviews: