Precision HWST Installation And Operating Instructions Manual Download Page 5

 

2.3 Uncrating 

2.3.1

 Care must be taken not to damage controls or deform the boiler sheet metal during removal of the crate. 

2.3.2

   If using pry bars or fork lifts, be certain to support the boiler weight by the skids or channel base. 

 

2.4   Placement 

CAUTION:  If the equipment is to be placed in a room with little or no ventilation, a supply of ducted filtered air 
may have to be brought to the lower portion of the control cabinet to limit the control cabinet interior 
temperature to 50°C (122°F) maximum.

 

CAUTION:

  If the equipment is to be placed in a room with little or no ventilation, a supply of ducted filtered air 

may have to be brought to the lower portion of the control cabinet to limit the control cabinet interior 
temperature to 50°C (122°F) maximum. 

2.

4.1   Provide a firm, level foundation for the equipment. 

 

NOTE:

  Standard electric boilers / water heaters are not suitable for placement on combustible flooring

 

2.4.2   

Leave a permanent space for element removal opposite element access panels as shown on the  

Dimensional Drawing (DD), and 36 inches opposite electrical panels

 

NOTE:

  Electric panels require 42” opposite any opposing conductive surface. 

 

2.4.3   

Be sure to keep electrical panels and controls covered at all times while construction work is in process.

      CAUTION:  

Do not use the equipment housing top for scaffolding. 

 

     Figure 1 

–  

     Minimum Clearance Recommendations and General Dimensional Data for Boiler Placement 

 
 
 

 
 
                                                        

 

 

 

 

 

 

 

 

 

 

3.0 INSTALLATION 

 

 

  3.1   Piping Connection 

   NOTE:

  Some of the following piping may have been completed at the Factory.

 

   3.1.1

   Boiler piping connections and values MUST comply with state and local codes, in addition to compliance with ANSI  

 

   piping requirements 
   

CAUTION:

  The pipe extensions outside the unit are usually the extensions of pipes which are permanently welded into  

   the unit’s vessel.  Normally the only removable (threaded) connection is the drain pipe.  DO NOT ATTEMPT TO REMOVE  
   ANY OTHER PIPING! 
 

Summary of Contents for HWST

Page 1: ...Installation and Operating Instructions ELECTRIC HOT WATER STEAM BOILERS...

Page 2: ...injury or property damage Read this manual thoroughly and follow the instructions herein The PRECISION Boilers shall be installed according to the procedures detailed in this manual or the Precision...

Page 3: ...2 Operating Instructions 9 5 2 2 Electric Door Interlocks 9 5 2 4 120 Volt Power Source 9 5 2 6 Alarm and Reset Circuits 9 5 2 7 Sequencing of Element Circuits 9 6 0 SEQUENCE OF OPERATION 6 1 Activati...

Page 4: ...f the authorities having jurisdiction 1 3 Recommendations 1 3 1 Preventative Maintenance A Preventative Maintenance Schedule is provided as a recommendation for periodic equipment Inspections Recordin...

Page 5: ...rs are not suitable for placement on combustible flooring 2 4 2 Leave a permanent space for element removal opposite element access panels as shown on the Dimensional Drawing DD and 36 inches opposite...

Page 6: ...ors The unit is equipped with grounding lugs s inside the power panel s The grounding conductors must be installed and sized in accordance with NEC Article 424 14 The recommended size is noted in the...

Page 7: ...fuses Then check the resistance phase to phase for all three phases Make sure that there are no short circuits phase to phase or phase to ground With a megger 500VDC minimum check contactor load side...

Page 8: ...t during the first day of operation the affected element will not be energized allowing the hot water to drive the moisture out at a controlled rate 4 4 3 Removal of Moisture in Element method 2 An al...

Page 9: ...same margin as specified for high limits to be above the controller setting 5 2 Operating Instructions 5 2 1 With the unit s control power ON OFF or ON OFF PREHEAT switch OFF close the main power swi...

Page 10: ...tactor coil circuits 6 2 2 Proportional Step Controls 6 2 2 1 Step Control Sequence The controller senses the unit s water temperature either via 135 ohm device or thermistor or steam pressure either...

Page 11: ...int the step controller should bring on nominally one half of the steps An adjustable proportional band is provided on the controller sensor to enable tuning the unit to system demand 7 1 2 Solid Stat...

Page 12: ...cause an automatic inverse change of 1 F at the control point NOTE Refer to the applicable vendor literature provided on both the setpoint controls and step controls installed in your boiler 8 0 PREV...

Page 13: ...k torque on element flange bolts The acceptable torque range is 10 15 ft lbs CAUTION Do not over tighten elements 8 4 2 Remove and replace any leaking elements or element gaskets Inspect handhole and...

Page 14: ...ement gaskets should be replaced immediately upon leak detection 8 5 1 Adequately tag wire and then remove wires from defective elements 8 5 2 Remove element by removing the four 4 attachment nuts 8 5...