2--6
Powerware BPIV (10 kVA--30 kVA) Installation and Operation
164201406 Rev. C 013004
2.
Remove front vented panel from Options cabinet. The Front panel is secured
with magnetic latches and is removed by pulling the panel straight forward to
disengage magnetic latches (see Figure 2---3).
3.
If the leveling feet are not fully retracted, turn the leveling feet until they are
retracted.
4.
Loosen screws securing Distribution Housing to Options cabinet. Lift
Distribution Housing up and remove from Options cabinet.
5.
Remove three bolts, (1) in Figure 2---4, securing the rear shipping bracket (3)
to the cabinet and three bolts (2) securing the bracket to the pallet. Remove
the rear shipping bracket. If installing cabinet permanently, retain shipping
brackets and securing hardware for later use.
6.
Remove three bolts, (1) in Figure 2---3, securing front shipping bracket (3) to
the pallet. Do not remove bolts (2) securing the bracket to the cabinet.
7.
Remove three bolts, (4) in Figure 2---4, securing removable skid (5) and
remove skid.
NOTE:
In the following step the pallet will tilt and act as a ramp once the cabinet is
rolled beyond the the center of the pallet. Make sure to restrain the cabinet
as it continues to roll down the pallet/ramp. The front shipping bracket will
act as a brake to assist restraining the cabinet.
WARNING:
Do not stand directly behind the pallet while unloading the cabinet If
unloading instructions are not closely followed, the cabinet may cause
serious injury.
8.
Slowly roll the cabinet toward the rear of the pallet. Once the pallet tilts,
continue rolling the cabinet down the pallet until the cabinet is clear of the
pallet.
9.
Remove three bolts, (2) in Figure 2---3, securing front shipping bracket to the
cabinet.
10.
If installing cabinet permanently, retain shipping brackets and hardware;
otherwise, discard or recycle the pallet and brackets in a responsible manner.
11.
Reinstall Distribution Housing over screws on rear of Options cabinet. Tighten
screws to secure Distribution Housing to Options cabinet.
12.
Roll cabinet to final installation location.
13.
If permanently mounting the system, proceed to step 16; otherwise, proceed to
step 14.
14.
Secure the Options cabinet in position by lowering the leveling feet, until
cabinet is not resting on the casters and the cabinet is level.
Summary of Contents for BPIV