background image

www.playcraftsystems.com

For Customer Service Call

800.333.8519 (U.S.A.) or 541.955.9199 (International)

SPIN MAX TOWER

INSTALLATION INSTRUCTIONS

Rev G

2/18/2021

PC-2476

Page 2 of 9

45"

45in

*

  36"

36in

 

36"

36in

MIN. 9"

(See Note D)

LOOSE FILL

Footing Detail

Footing Pin

Blocking, see

Installers Manual

Concrete Footing

2b Stone, drain rock

Optional Filter Fabric over

Pea Gravel (for drainage)

(Finish Grade)

LOOSE FILL SURFACING

MATERIAL SHOWN:

9" compressed or 12"

uncompressed depth.

Compressed depth shown.

(See Note E)

(Top of Soil)

Undisturbed Soil

Top of Surfacing Label

C

P.I.P. / TILE

Footing Detail

 Varies 

3"

3in

**

DETAIL C

SCALE 1 : 12

(Finish Grade)

(Top of Soil)

Optional Filter Fabric over

Pea Gravel (for drainage)

Concrete Footing

P.I.P. / TILE 
SURFACING MATERIAL

Step 1

 

Refer to Footing Layout and mark 

footing hole location. Dig (1) Ø 36" 

footing hole. Refer to Footing 

Detail for depth and details.

IMPORTANT:

 For areas with soft 

soil conditions, larger footings may 

be required. 
* Footing depth must be adjusted 

to compensate for the 

depth/thickness requirements of 

selected safety surfacing. See 

Section 06.1 of the Installation 

Manual.

** For P.I.P. / Rubber Tile Surfacing footing depth 

must be adjusted to ensure Leg Hardware and 

Speed Limiter Cover are accessible for maintenance.

Summary of Contents for PC-2476

Page 1: ...7 standards The maximum rotations per minute for Spin Max events shall be no greater than 31 Test with the applied force of a male adult between the ages of 18 to 34 150 lbs 68 kgs to 190 lbs 86 kgs a...

Page 2: ...d Soil Top of Surfacing Label C P I P TILE Footing Detail Varies 3 3in DETAIL C SCALE 1 12 Finish Grade Top of Soil Optional Filter Fabric over Pea Gravel for drainage Concrete Footing P I P TILE SURF...

Page 3: ...MAX TOWER INSTALLATION INSTRUCTIONS Rev G 2 18 2021 PC 2476 Page 3 of 9 72 72in Refer to current ASTM 1487 standards The Use Zone for Rotating Play equipment shall be no less than 72 1829mm in all di...

Page 4: ...RM 3 8 Thin Lock Nut 3 8 x 7 8 O D Washer 3 8 x 2 1 4 Button Head Bolt 3 8 x 7 8 O D Washer 1 3 8 x 5 8 THICK NYLON WASHER 2 1 2 WHEEL 1 3 8 x 5 8 THICK NYLON WASHER Step 4 Factory Assembled Attach 2...

Page 5: ...UBLE SEAL BALL BEARING SNAP RING SPIN MAX BEARING HOUSE SPIN MAX BASE TOWER POST 3 8 x 1 O D Washer 3 8 Lock Nut Step 5 Factory Assembled Insert Tower Post through Spin Max Base and attach to Spin Max...

Page 6: ...D Washer 3 8 x 1 11 16 Button Head Bolt 3 8 x 3 4 Button Head Bolt 3 8 x 7 8 O D Washer 3 8 Thin Lock Nut 3 8 x 1 3 8 Barrel Nut 1 2 SAE Washer TOP TRIM BOTTOM TRIM 3 8 x 1 O D Washer 3 8 x 1 1 2 But...

Page 7: ...HTENING TORQUE FOR HARDWARE section of the Installation Manual Step 13 Plumb and level entire component Pour concrete into footing hole Allow at least 72 hours to cure before proceeding to next step S...

Page 8: ...Top Plate Trim Bottom 1 EE 0228 TOP Spin Max Top Plate Trim Top 1 FS PC2476 BHS Spin Max Bearing House 1 FS PC2476 LTR Speed Limiter Arm 3 FS PC2476 PST Spin Max Tower Post 1 FS PC2476 RNG Spin Max S...

Page 9: ...d 3 8 thick steel plug and 3 16 thick steel clevis and will have a multi stage baked on powder coat finish SPEED LIMITER BASE Shall be fabricated using 1 4 thick steel plate with welded 3 16 thick ste...