Page 7 of 9
3/8" x 5-1/2"
Hex Bolt
FIGURE 8
1/2" Lock Nut
1/2" Washer x
.116 Thick
POST SUPPORT
1/2" x 1-3/4"
Button Head Bolt
1/2" Washer x
.116 Thick
3/8" Hex Nut
POST SUPPORT
FIGURE 9
SPIN MAX BEARING
HOUSE
1/2" x 2" Hex Bolt
(Tension Adjustment Bolt)
FIGURE 10
1/2" Jam Nut
Step 10
Install footing pin into Post Support as shown in Figure 8.
(See Note A)
Step 11
Attach Post Support to Spin Max Bearing House as
shown in Figure 9 and place Spin Max Tower
into footing hole. (See Notes A & B)
Step 12
Fully tighten all fasteners according to the
"TIGHTENING TORQUE FOR HARDWARE"
section of the Installation Manual.
Step 13
Plumb and level entire component. Pour concrete
into footing hole. Allow at least 72 hours to cure
before proceeding to next step. (See Note B)
Step 14
Affix "Top of Surfacing" label to base of Spin Max Tower
indicating the top of minimum required surfacing depth.
(See Note E)
Step 15
To set brake tension, remove Cover Panel Halves, loosen 1/2"
Jam Nuts and adjust all Tension Adjustment Bolts by 1/4 turn
as shown in Figure 10. Test number of revolutions per minute.
Tighten or loosen bolts evenly using 1/4 turn increments.
Tighten 1/2" Jam Nuts when brake tension is properly set.
(See Note C)
NOTE:
Do not over tighten Tension Adjustment Bolts.
If any questions or concerns arise during the installation
or maintenance of the Spin Max brake, please contact the
factory and ask to speak to a customer service representative
at
1-800-333-8519
.